File #: Res. 2019-190R    Version: 1 Name:
Type: Resolution Status: Individual Consideration
File created: 9/5/2019 In control: City Council
On agenda: 9/30/2019 Final action:
Title: Consider approval of Resolution 2019-190R, approving the award of a Construction Contract to the Brandt Companies, LLC for upgrades to the Redwood, McCarty, and Strahan Electric Substations in the Amount of $1,870,206.58; authorizing the City Manager, or his designee, to execute the contract and associated documents on behalf of the City; and declaring an effective date.
Attachments: 1. Resolution, 2. 219-310 Bid Tabulation.pdf
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
AGENDA CAPTION:
Title
Consider approval of Resolution 2019-190R, approving the award of a Construction Contract to the Brandt Companies, LLC for upgrades to the Redwood, McCarty, and Strahan Electric Substations in the Amount of $1,870,206.58; authorizing the City Manager, or his designee, to execute the contract and associated documents on behalf of the City; and declaring an effective date.
Body
Meeting date: September 30, 2019

Department: Public Services - Tom Taggart Executive Director (by Lynda Williams, Purchasing Manager)

Amount & Source of Funding
Funds Required: $1,870,206.58
Account Number: C388 51538163-70200 / C649 51538159-70200 / C674 51538163-70200
Funds Available: $2,629,606.98
Account Name: Capital Project Debt Funded-Redwood Station, Strahan Substation, McCarty Lane Substation

Fiscal Note:
Prior Council Action: Approval of Capital Improvement Project C388 for the upgrade of the Redwood Substation; approval of the purchase of the large power transformer for this project through resolution 2017-155R. Approval of C649 for the upgrade of the Strahan Substation. Approval of C674 for the upgrade of the McCarty Substation.

City Council Strategic Initiative: [Please select from the dropdown menu below]
Choose an item.
Choose an item.
Choose an item.

Comprehensive Plan Element (s): [Please select the Plan element(s) and Goal # from dropdown menu below]
? Economic Development - Choose an item.
? Environment & Resource Protection - Choose an item.
? Land Use - Choose an item.
? Neighborhoods & Housing - Choose an item.
? Parks, Public Spaces & Facilities - Choose an item.
? Transportation - Choose an item.
? Not Applicable

Master Plan: [Please select the corresponding Master Plan from the dropdown menu below (if applicable)]
Choose an item.


Background Information:
San Marcos Electric Utility Department has identified Redwood, McCarty, and Strahan substations as needing upgrades to increase reliability.

The City's assets in the Redwoo...

Click here for full text