AGENDA CAPTION:
Title
Consider approval of Resolution 2019-115R, approving the third Change in Service to the agreement with American StructurePoint, Inc. relating to the Sessom Drainage Improvements Project to add engineering design services for additional Storm Drain, Water and Wastewater Pipeline Improvements in the amount of $146,418.62; authorizing the City Manager or his designee to execute the appropriate documents to implement the change in service; and declaring an effective date.
Body
Meeting date: June 18, 2019
Department: Engineering & CIP
Amount & Source of Funding
Funds Required: $146,418.620
Account Number: C419
Funds Available: $250,000
Account Name: Sessom Improvements at Academy
Fiscal Note:
Prior Council Action: NA
City Council Strategic Initiative: [Please select from the dropdown menu below]
Choose an item.
Choose an item.
Choose an item.
Comprehensive Plan Element (s): [Please select the Plan element(s) and Goal # from dropdown menu below]
? Economic Development - Choose an item.
? Environment & Resource Protection - Choose an item.
? Land Use - Choose an item.
? Neighborhoods & Housing - Choose an item.
? Parks, Public Spaces & Facilities - Choose an item.
? Transportation - Safe, Well coordinated transportation system implemented in an environmentally sensitive manner
? Not Applicable
Master Plan: [Please select the corresponding Master Plan from the dropdown menu below (if applicable)]
Choose an item.
Background Information:
Residential structures and properties flood and drain poorly after every rainfall event along Academy Street between Orchard Street and Sessom Drive. Grate inlets along Orchard Street clog during every rainfall event and prevent adequate drainage. The existing drainage system (private) is undersized and TX State has exacerbated flooding by tying in drainage from a curb inlet into Academy.
During 60% design meeting with TxState, it was agreed to revise the project limits from Alamo St to Comanche ...