File #: Res. 2019-25R    Version: 1 Name:
Type: Resolution Status: Individual Consideration
File created: 1/7/2019 In control: City Council
On agenda: 2/5/2019 Final action:
Title: Consider approval of Resolution 2019-25R, approving an Advance Funding Agreement with the State of Texas, acting through the Texas Department of Transportation (CSJ Nos. 0016-09-040 and 0366-01-079), for the Guadalupe Street Improvements Project from University Drive to Grove Street, that includes bike lanes, parking, bike signals and signs with an estimated cost of participation by the City in the amount of $26,777; authorizing the City Manager to execute said agreement on behalf of the City; and declaring an effective date.
Attachments: 1. Resolution, 2. S. Guadalupe St Pavement Markings Plans - 30% Submittal.pdf, 3. Approved AFA Loop 82 City of SanMarcos.pdf
AGENDA CAPTION:
Title
Consider approval of Resolution 2019-25R, approving an Advance Funding Agreement with the State of Texas, acting through the Texas Department of Transportation (CSJ Nos. 0016-09-040 and 0366-01-079), for the Guadalupe Street Improvements Project from University Drive to Grove Street, that includes bike lanes, parking, bike signals and signs with an estimated cost of participation by the City in the amount of $26,777; authorizing the City Manager to execute said agreement on behalf of the City; and declaring an effective date.
Body
Meeting date: February 5, 2019

Department: Engineering & CIP

Amount & Source of Funding
Funds Required: $26,777
Account Number: C477
Funds Available: $506,000
Account Name: Debt funded CIP Project-Guadalupe/LBJ Improvements

Fiscal Note:
Prior Council Action: Click or tap here to enter text.

City Council Strategic Initiative: [Please select from the dropdown menu below]
City Facilities
Choose an item.
Choose an item.
Comprehensive Plan Element (s): [Please select the Plan element(s) and Goal # from dropdown menu below]
? Economic Development - Choose an item.
? Environment & Resource Protection - Choose an item.
? Land Use - Choose an item.
? Neighborhoods & Housing - Choose an item.
? Parks, Public Spaces & Facilities - Choose an item.
? Transportation - Multimodal transportaion network to improve accessibility and mobility, minimize congestion and reduce pollution
? Not Applicable

Master Plan: [Please select the corresponding Master Plan from the dropdown menu below (if applicable)]
Transportation Master Plan

Background Information:
An Advanced Funding Agreement (AFA) is required between the Texas Department of Transportation (TxDOT) and the City of San Marcos (City) for improvements to Guadalupe Street from University Drive to Grove Street; including bike lanes and revised on-street parking layout; construction of TIRZ funded sidewalk improvements along the east side of Guadalupe between MLK Dr...

Click here for full text