AGENDA CAPTION:
Title
Consider approval of Resolution 2021-30R, approving a Change in Service to the agreement with Kimley-Horn and Associates, Inc. to add additional engineering design services for the Hopkins Street Improvements project in the estimated amount of $57,915.00; authorizing the City Manager or his designee to execute the appropriate documents to implement the Change in Service; and declaring an effective date.
Body
Meeting date: February 24, 2021
Department: Engineering & CIP, Laurie Moyer, Director (by Lynda Williams, Purchasing Manager)
Amount & Source of Funding
Funds Required: $57,915.00
Account Number: C594
Funds Available: $871,903.47
Account Name: Hopkins St Imps Moore to Guadalupe
Fiscal Note:
Prior Council Action: Professional engineering services contract (219-129.5) award on January 20, 2020
City Council Strategic Initiative: [Please select from the dropdown menu below]
Downtown Vitality
Choose an item.
Choose an item.
Comprehensive Plan Element (s): [Please select the Plan element(s) and Goal # from dropdown menu below]
? Economic Development - Choose an item.
? Environment & Resource Protection - Choose an item.
? Land Use - Choose an item.
? Neighborhoods & Housing - Choose an item.
? Parks, Public Spaces & Facilities - Choose an item.
? Transportation - Multimodal transportaion network to improve accessibility and mobility, minimize congestion and reduce pollution
? Core Services
? Not Applicable
Master Plan: [Please select the corresponding Master Plan from the dropdown menu below (if applicable)]
Transportation Master Plan
Background Information:
This Council request is to approve the Authorization for Change in Service (ACIS#1) to add engineering services for an option to include: improvements to Moore Street from Hopkins Street to Hutchison Street, traffic analysis for Moore Street between Hopkins Street and Hutchison Street, an option for a southbound left turn lane along Moore Street at Hutchison Street, and...
Click here for full text