File #: Res. 2021-36R    Version: 1 Name:
Type: Resolution Status: Individual Consideration
File created: 1/15/2021 In control: City Council
On agenda: 2/24/2021 Final action:
Title: Consider approval of Resolution 2021-36R, approving the award of a construction contract to Lambda Construction I, LLC, for construction of the Rattler Electric Substation in the estimated amount of $6,448,491.00; authorizing the City Manager or his designee to execute the contract on behalf of the City; and declaring an effective date.
Attachments: 1. Resolution, 2. Res 2019-161, 3. 221-010 Bid Tabulation, 4. 2019-005_amending the City’s 2018-2019 Fiscal Year Budget, 5. 2019-021R Amended 380, 6. 2019-022R CIAC, 7. 2020-03R approving Rattler Substation XFMR Purchase

AGENDA CAPTION:

Title

Consider approval of Resolution 2021-36R, approving the award of a construction contract to Lambda Construction I, LLC, for construction of the Rattler Electric Substation in the estimated amount of $6,448,491.00; authorizing the City Manager or his designee to execute the contract on behalf of the City; and declaring an effective date.

Body

Meeting date:  February 24, 2021

 

Department:  Public Services - Tom Taggart, Director (by Lynda Williams, Purchasing Manager)

 

Amount & Source of Funding
Funds Required:
  $6,448,491.00

Account Number:  51538112-70200

Funds Available:  Elect CIP - CAP PR MJR

Account Name:  Click or tap here to enter text.

 

Fiscal Note:
Prior Council Action:  February 5, 2019 - Ordinance 2019-05 was approved on second reading allocating a not to exceed budget of $8,250,000 for Rattler Electric Substation construction costs. CIP project FY146 was established to track the project and was cash funded to cover the costs of professional services for surveys, detailed engineering studies and design, with the balance of the project bond funded.

 

At the same time, an amended Chapter 380 economic development incentive agreement was approved through resolution 2019-021R, and a Contribution in Aid of Construction agreement was approved via resolution 2019-22R.  Both the Chapter 380 and CIAC require the construction of Rattler Substation.

 

Resolution 2019-161R authorized an Engineering Services Contract with LCRA for the design of Rattler Substation.

 

Resolution 2020-03R approved the purchase of a power transformer for Rattler Substation.

 

City Council Strategic Initiative:  [Please select from the dropdown menu below]

N/A

Choose an item.

Choose an item.

 

Comprehensive Plan Element (s): [Please select the Plan element(s) and Goal # from dropdown menu below]
Economic Development - Choose an item.
Environment & Resource Protection - Choose an item.
Land Use - Choose an item.
Neighborhoods & Housing - Choose an item.
Parks, Public Spaces & Facilities - Choose an item.
Transportation - Choose an item.

Core Services

Not Applicable

Master Plan
: [Please select the corresponding Master Plan from the dropdown menu below (if applicable)]
San Marcos Electric Utility Master Plan


Background Information:

San Marcos Electric Utility is seeking a General Contractor to construct a new electric substation to meet the growing loads in the industrial area near Clovis Barker.

 

This request is for Council to award to the highest ranked contractor based on the total scores and ranking.  In accordance with Texas Government Code 2269 and City Purchasing Policy, the City solicited Competitive Sealed Proposals #221-010, for Rattler Substation.  On December 17, 2020, five (5) proposals were received. All proposals were evaluated by a City-staffed evaluation committee.  The evaluation committee recommends Lambda Construction I, LLC, New Braunfels, TX as the top-ranked contractor based on criteria published in the solicitation to determine the best value to the City of San Marcos.

 

Criteria consisted of:

                     Prior Experience with Projects of Similar, Size, Scope, and Scale - 40 max points

                     Safety Record - 5 max points

                     Prior Experience of Project Manager and Project Superintendent - 10 max points

                     Project Approach and Schedule - 10 max points

                     Price Proposal - 35 max points

 

Results from the final composite of all three evaluator scores by total and ranking are below:

FIRMS

Lambda Construction, LLC

289.00

1.0

Saber Power Services, LLC

282.69

2.0

Sayers Construction, LLC

234.58

3.0

Primoris T&D Services

226.94

4.0

Pike Electric, LLC

211.05

5.0

 

The scoring of the price component of the evaluation factors was calculated on a percentage of points based on a percentage comparison with the lowest Base Proposal Price. Lambda Construction, LLC was the lowest price, and received the full 35 points. All proposals had discrepancies in calculation of unit price totals which resulted in revised total base proposal amount.

Lambda  Construction

Sayers Construction, LLC

Primoris T&D Services

Saber Power Services, LLC

Pike Electric, LLC

$6,448,491.00

$7,558,832.59

$7,057,650.52

$6,792,300.00

$7,436,869.20

 

The top-ranked contractor, Lambda Construction I, LLC is recommended for award as the best value based on qualifications, experience, reputation, safety and price for the contract amount of $6,448,491.

 

Council Committee, Board/Commission Action:
Click or tap here to enter text.

Alternatives:

Click or tap here to enter text.


Recommendation: 

City staff recommends awarding a contract to Lambda Construction, LLC for Public Services in the amount of $6,448,491.