File #: Res. 2021-31R    Version: 1 Name:
Type: Resolution Status: Individual Consideration
File created: 1/19/2021 In control: City Council
On agenda: 2/24/2021 Final action:
Title: Consider approval of Resolution 2021-31R, approving an Advanced Funding Agreement (AFA) between the City of San Marcos and the Texas Department of Transportation (TxDOT) for utility betterments along IH35 from south of SH 80 (Hopkins St) to north of RM 12 (Wonder World Dr); in the amount of $185,195.28, to be paid by the City of San Marcos, at least 45 days prior to the date set by TxDOT, for receipt of the construction bids; authorizing the City Manager to execute the agreement; and declaring an effective date.
Attachments: 1. Resolution, 2. AFA_IH 35_SH 123_COSM-Water_CSJ 0016-03-114_DRAFT 02.10.21.pdf, 3. 01_0016-03-114_100% W_WW Plan.pdf, 4. project limits.pdf
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

AGENDA CAPTION:

Title

Consider approval of Resolution 2021-31R, approving an Advanced Funding Agreement (AFA) between the City of San Marcos and the Texas Department of Transportation (TxDOT) for utility betterments along IH35 from south of SH 80 (Hopkins St) to north of RM 12 (Wonder World Dr); in the amount of $185,195.28, to be paid by the City of San Marcos, at least 45 days prior to the date set by TxDOT, for receipt of the construction bids; authorizing the City Manager to execute the agreement; and declaring an effective date.

 

Body

Meeting date:  February 24, 2021

 

Department:  Engineering & CIP

 

Amount & Source of Funding
Funds Required:
  $185,195.28

Account Number:  C629

Funds Available:  $458,286.34

Account Name:  IH-35 Utility Relocations

 

Fiscal Note:
Prior Council Action: NA

City Council Strategic Initiative:  [Please select from the dropdown menu below]

City Facilities

Choose an item.

Choose an item.

Comprehensive Plan Element (s): [Please select the Plan element(s) and Goal # from dropdown menu below]
Economic Development - Choose an item.
Environment & Resource Protection - Choose an item.
Land Use - Choose an item.
Neighborhoods & Housing - Choose an item.
Parks, Public Spaces & Facilities - Choose an item.
Transportation - Multimodal transportaion network to improve accessibility and mobility, minimize congestion and reduce pollution

Not Applicable

Master Plan
: [Please select the corresponding Master Plan from the dropdown menu below (if applicable)]
Choose an item.


Background Information:

Texas Department of Transportation’s (TxDOT) I-35 @ SH123 project consists of intersection improvements at I-35 and SH 123 and ramp reversals between SH 80 (Hopkins St) and RM 12 (Wonder World Dr). The purpose of this project is to improve safety and mobility.

 

Project Description:

 

                     Reconstruct and improve the SH 123 intersection

                     Reverse two ramps along the northbound frontage road between SH 80 and SH 123

                     Reverse one entrance ramp along the southbound frontage road between SH 80 and SH 123

                     Realign the existing southbound exit ramp to SH 123 (CM Allen Parkway)

                     Relocate the entrance ramp along the southbound frontage road from SH 80

                     Reconstruct portions of the northbound and southbound frontage roads, including improving bicycle and pedestrian accommodations

                     Reconstruct the frontage road bridges over Willow Springs Creek

                     Raise and reconstruct the northbound frontage road bridge over the San Marcos River

                     Widen the southbound frontage road bridge over the San Marcos River

                     Reconstruct the main lanes and bridge over SH 123

                     Add auxiliary lanes, or extended entrance/exit lanes, to the main lanes and frontage roads

 

Project Schedule:

 

Design Completion: anticipated early 2021

Construction Letting: anticipated mid 2021

Construction Start: anticipated late 2021

Construction Completion: anticipated late 2023

 

An Advanced Funding Agreement (AFA) is required between the Texas Department of Transportation (TxDOT) and the City of San Marcos (City) to include water and wastewater betterments along IH 35 from south of SH 80 to north of RM 12. The City will be responsible for maintenance of locally owned roads and locally owned facilities after the completion of the work. TxDOT will be responsible for maintenance of the State Highway System after completion of the work, unless otherwise included in an existing maintenance agreement with the City. The estimated total construction cost for the utility relocation and betterments is $2,708,686.46

 

Estimated total payment by the City to TxDOT is $185,195.28. The City shall pay TxDOT the full amount and shall remit the payment to TxDOT at least 45 days prior to the date set for receipt of the construction bids.

 

 

Council Committee, Board/Commission Action:
NA

Alternatives:

NA


Recommendation: 

Staff recommends approval of this Resolution