AGENDA CAPTION:
Title
Consider approval of Resolution 2021-03R, approving a Developer Participation Agreement providing for the City to participate in the cost of extending wastewater infrastructure from the Trace Subdivision to the Posey Business Park area in the amount of $850,248; authorizing the City Manager or his designee, to execute said agreement; and declaring an effective date.
Body
Meeting date: January 5, 2021
Department: Engineering & CIP
Amount & Source of Funding
Funds Required: $850,247.85
Account Number: IMPWW
Funds Available: $4,889,144.36
Account Name: Impact Fees Wastewater
Fiscal Note:
Prior Council Action: July 5, 2017 - Presentation and Direction to Staff
City Council Strategic Initiative: [Please select from the dropdown menu below]
Workforce Development
Choose an item.
Choose an item.
Comprehensive Plan Element (s): [Please select the Plan element(s) and Goal # from dropdown menu below]
? Economic Development - Diverse Local Economic Environment
? Environment & Resource Protection - Choose an item.
? Land Use - Choose an item.
? Neighborhoods & Housing - Choose an item.
? Parks, Public Spaces & Facilities - Choose an item.
? Transportation - Choose an item.
? Core Services
? Not Applicable
Master Plan: [Please select the corresponding Master Plan from the dropdown menu below (if applicable)]
Wastewater Master Plan
Background Information:
The Posey Road area between Interstate Highway 35 and Hunter Road is developing as an Industrial Business Park with City water service and onsite septic systems. The area is anticipated to be annexed with further development of the tracts of land. It was agreed with property owner participation the extension of City wastewater service would benefit both the business park and the City for continued growth in this area. This developer participation agreement provides for a wastewater extension from the Trace Subdivision to the Posey Business Park area sizing lines for future extension...