File #: Res. 2020-254R    Version: 1 Name:
Type: Resolution Status: Individual Consideration
File created: 10/19/2020 In control: City Council
On agenda: 11/17/2020 Final action:
Title: Consider approval of Resolution 2020-254R, approving the award of a contract to Electro Technical Industries, Inc for the San Marcos Electrical Utility Switchgear Building in the estimated amount of $802,300.00; authorizing the City Manager or his designee to execute the agreement on behalf of the City; and declaring an effective date.
Attachments: 1. Resolution -SMEU Switchgear Building.pdf, 2. 220-255 Bid Tabulation

AGENDA CAPTION:

Title

Consider approval of Resolution 2020-254R, approving the award of a contract to Electro Technical Industries, Inc for the San Marcos Electrical Utility Switchgear Building in the estimated amount of $802,300.00; authorizing the City Manager or his designee to execute the agreement on behalf of the City; and declaring an effective date.

 

Body

Meeting date:  November 17, 2020

 

Department:  Public Services - Tom Taggart, Director (by Lynda Williams, Purchasing Manager)

 

Amount & Source of Funding
Funds Required:
  $802,300

Account Number:  C652 51538170-70200

Funds Available:  $5,918,534

Account Name:  Wastewater Treatment Plant Electric Backup Feed

 

Fiscal Note:
Prior Council Action: Approval of CIP C652 in FY18 budget cycle

City Council Strategic Initiative:  [Please select from the dropdown menu below]

N/A

Choose an item.

Choose an item.

 

Comprehensive Plan Element (s): [Please select the Plan element(s) and Goal # from dropdown menu below]
Economic Development - Choose an item.
Environment & Resource Protection - Choose an item.
Land Use - Choose an item.
Neighborhoods & Housing - Choose an item.
Parks, Public Spaces & Facilities - Choose an item.
Transportation - Choose an item.

Core Services

Not Applicable

Master Plan
: [Please select the corresponding Master Plan from the dropdown menu below (if applicable)]
Choose an item.


Background Information:

The medium voltage switchgear building is a main component for achieving project scope of increasing the electric reliability at the City’s wastewater treatment plant. Once this building is in service, the City will be able to automatically transfer the plant to the backup source during outages and will gain more detailed data about the treatment plant’s energy usage and power quality.

 

Eight (8) bids were received on October 1, 2020. The apparent low bidder failed to comply with the bidding requirements, and is therefore deemed nonresponsive making the bidder disqualified. Award is recommended to the lowest responsible bidder, Electro Technical Industries, Inc., from Houston, Texas, that did submit a bid responsive to all bid requirements, in the amount of $802,300.

 

Council Committee, Board/Commission Action:
N/A

Alternatives:

None.  This building is integral to the design for providing redundant feeds throughout the WWTP.


Recommendation: 

Staff recommends award of a construction contract to Electro Technical Industries, Inc. in the amount of $802,300.