Title: Consider approval of Resolution 2019-131R, awarding a construction contract to the Brandt Companies, LLC for upgrades to the Canyon and San Marcos substations in the amount of $548,042.04; authorizing the City Manager, or his designee, to execute all appropriate contract documents on behalf of the City; and declaring an effective date.
Attachments: 1. Resolution, 2. Recommendation Memo, 3. Proposal Log
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
AGENDA CAPTION:
Title
Consider approval of Resolution 2019-131R, awarding a construction contract to the Brandt Companies, LLC for upgrades to the Canyon and San Marcos substations in the amount of $548,042.04; authorizing the City Manager, or his designee, to execute all appropriate contract documents on behalf of the City; and declaring an effective date.
Body
Meeting date: August 6, 2019

Department: Public Services, Tom Taggart - Director (by Lynda Williams, Purchasing Manager).

Amount & Source of Funding
Funds Required: $548,042.04
Account Number: FY153 51538112-70200
Funds Available: $720,000
Account Name: Canyon and San Marcos Control Buildings

Fiscal Note:
Prior Council Action: Click or tap here to enter text.

City Council Strategic Initiative: [Please select from the dropdown menu below]
N/A
Choose an item.
Choose an item.

Comprehensive Plan Element (s): [Please select the Plan element(s) and Goal # from dropdown menu below]
? Economic Development - Choose an item.
? Environment & Resource Protection - Choose an item.
? Land Use - Choose an item.
? Neighborhoods & Housing - Choose an item.
? Parks, Public Spaces & Facilities - Choose an item.
? Transportation - Choose an item.
? Not Applicable

Master Plan: [Please select the corresponding Master Plan from the dropdown menu below (if applicable)]
Choose an item.


Background Information:
Both Canyon and San Marcos substation control buildings flood during major events, creating significant risks to equipment damage and mis-operations that will affect system reliability. Moving the protection and control systems from the existing buildings into the new, elevated LCRA control buildings was a capital outlay request approved by Council during the FY19 budget process. Additionally, the project to replace the distribution breakers and relay panels at the Canyon substation was combined into this project to avoid overlapping scopes.