Consider approval of Resolution 2019-130R, approving the purchase of twelve 15.5 kV R-MAG Circuit Breakers for the Public Services Department, Electric Utilities Division, in the total amount of $223,450 from Wesco Distribution, Inc. through the Texas Cooperative Purchasing Network Contract #R142106; authorizing the City Manager or his designee to execute the appropriate purchasing documents on behalf of the City; and declaring an effective date.
Body
Meeting date: August 6, 2019
Department: Public Services Department - Tom Taggart, Director (By Lynda Williams, Purchasing Manager)
Amount & Source of Funding
Funds Required: $131,625 / $91,825
Account Number: C388 51538163-70200 / C649 51538159-70200
Funds Available: $2,000,000 / %522,925
Account Name: Click or tap here to enter text.
Fiscal Note:
Prior Council Action: Approval of Capital Improvement Project C388 for the upgrade of the Redwood Substation; approval of the purchase of the large power transformer for this project through resolution 2017-155R. Approval of C649 for the upgrade of the Strahan Substation upgrade.
City Council Strategic Initiative: [Please select from the dropdown menu below]
N/A
Choose an item.
Choose an item.
Comprehensive Plan Element (s): [Please select the Plan element(s) and Goal # from dropdown menu below]
? Economic Development - Choose an item.
? Environment & Resource Protection - Choose an item.
? Land Use - Choose an item.
? Neighborhoods & Housing - Choose an item.
? Parks, Public Spaces & Facilities - Choose an item.
? Transportation - Choose an item.
? Not Applicable
Master Plan: [Please select the corresponding Master Plan from the dropdown menu below (if applicable)]
Choose an item.
Background Information:
The City's assets in the Redwood Substation are aged and obsolete. A substation upgrade project was approved to replace the power transformer and distribution breakers, replace the relaying and control systems, and update the s...