File #: ID#19-042    Version: 1 Name:
Type: Discussion Item Status: Individual Consideration
File created: 2/21/2019 In control: City Council
On agenda: 3/19/2019 Final action:
Title: Consider approval, by motion, of Change Order # 1 for Contract 218-010, Smith Contracting Co., Inc. for sanitary sewer and water infrastructure relocation/replacement for the CM Allen Roadway Reconstruction Project in the amount of $131,494.16.
Attachments: 1. CM Allen CO#1 Map.pdf, 2. CO #1
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
AGENDA CAPTION:
Title
Consider approval, by motion, of Change Order # 1 for Contract 218-010, Smith Contracting Co., Inc. for sanitary sewer and water infrastructure relocation/replacement for the CM Allen Roadway Reconstruction Project in the amount of $131,494.16.
Body
Meeting date: March 19, 2019

Department: Engineering and Capital Improvements, Laurie Moyer, Director (by Lynda Williams, Purchasing Manager)

Amount & Source of Funding
Funds Required: $131,494.16
Account Number: C557
Funds Available: $170,000.00
Account Name: CM Allen Reconstruction

Fiscal Note:
Prior Council Action: June 19, 2018: Approval of construction contract 218-010 for CM Allen in the amount of $2,775,080.54.

City Council Strategic Initiative: [Please select from the dropdown menu below]
N/A
Stormwater
Choose an item.
Comprehensive Plan Element (s): [Please select the Plan element(s) and Goal # from dropdown menu below]
? Economic Development - Choose an item.
? Environment & Resource Protection - Choose an item.
? Land Use - Choose an item.
? Neighborhoods & Housing - Choose an item.
? Parks, Public Spaces & Facilities - Choose an item.
? Transportation - Safe, Well coordinated transportation system implemented in an environmentally sensitive manner
? Not Applicable

Master Plan: [Please select the corresponding Master Plan from the dropdown menu below (if applicable)]
Transportation Master Plan

Background Information:
The CM Allen Roadway Reconstruction Project consists of reconstructing the roadway from Hopkins to University. Other project components include: 12-foot multi-use pathway from Hopkins to Dog Beach on riverside, 6-foot sidewalks on downtown side, 10-foot multi-use pathway link to river, street parallel parking, trees and landscaping, street and pedestrian lighting like downtown, cross walk at Hutchison, realignment of the Hutchison and river park parking lot intersections, and Green Infrastructure.

This CO #1 consists of relocating/replacing two existing...

Click here for full text