AGENDA CAPTION:
Title
Consider approval, by motion, of Change Order #1 for the Victory Gardens Subdivision Improvement Project in the amount of $142,076.00 adding locations for water and wastewater replacement to replace all of the water and wastewater infrastructure within the Project limits.
Body
Meeting date: February 19, 2019
Department: CIP/Engineering, Laurie Moyer, Director (by Lynda Williams, Purchasing Manager)
Amount & Source of Funding
Funds Required: $142,076.00
Account Number: C281 W/WW
Funds Available: $2,554,065.54
Account Name: Debt Funded CIP Project -Victory Gardens Subdivision Improvements
Fiscal Note:
Prior Council Action: June 5, 2018 - Award of Construction Contract to Cox Commercial Construction, LLC for $8,260,891.20
City Council Strategic Initiative: [Please select from the dropdown menu below]
N/A
Choose an item.
Choose an item.
Comprehensive Plan Element (s): [Please select the Plan element(s) and Goal # from dropdown menu below]
? Economic Development - Choose an item.
? Environment & Resource Protection - Choose an item.
? Land Use - Choose an item.
? Neighborhoods & Housing - Protected Neighborhoods in order to maintain high quality of life and stable property values
? Parks, Public Spaces & Facilities - Choose an item.
? Transportation - Choose an item.
? Not Applicable
Master Plan: [Please select the corresponding Master Plan from the dropdown menu below (if applicable)]
Choose an item.
Background Information:
The Victory Garden Subdivision Improvement project consists of replacing old and undersized water, wastewater and storm sewer lines as well as reconstruction of pavement, curbs and sidewalks.
Change Order #1 adds locations for water and wastewater replacement to replace all of the water and wastewater infrastructure within the project limits. Early in the design phase, water/wastewater utility replacement emphasis was placed on areas reported to be more problematic in order to keep the project within bud...
Click here for full text