File #: Res. 2018-04R    Version: 1 Name:
Type: Resolution Status: Individual Consideration
File created: 12/19/2017 In control: City Council
On agenda: 1/16/2018 Final action:
Title: Consider approval of Resolution 2018-04R, awarding a contract to T.F. Harper and Associates, LP. for construction of a playscape at Children's Park in the amount of $1,251,516.00 contingent upon the Contractor's timely submission of sufficient bonds and insurance as required; through an Interlocal Agreement with Region 19 education service center; authorizing the City Manager or designee to execute the appropriate purchasing documents on behalf of the City and declaring an effective date.
Attachments: 1. Resolution, 2. Playscape Install newA, 3. Rendering for Playscape II, 4. Existing Playscape 1, 5. Existing Playscape 2, 6. Existing Playscape 3, 7. Existing Playscape 4, 8. Existing Playscape 5

AGENDA CAPTION:

Title

Consider approval of Resolution 2018-04R, awarding a contract to T.F. Harper and Associates, LP. for construction of a playscape at Children’s Park in the amount of $1,251,516.00 contingent upon the Contractor’s timely submission of sufficient bonds and insurance as required; through an Interlocal Agreement with Region 19 education service center; authorizing the City Manager or designee to execute the appropriate purchasing documents on behalf of the City and declaring an effective date.

Body

Meeting date:  1/16/2018

 

Department:  Community Services Department - Rodney Cobb, Executive Director (By Cheryl Pantermuehl, Purchasing Manager)

 

Amount & Source of Funding
Funds Required:
  $1,251,516.00

Account Number:  50036959.70200 C439-General-Construction

Funds Available:  $1,350,000

Account Name:  PARD GF Debt 2016

 

Fiscal Note:
Prior Council Action: Click or tap here to enter text.

City Council Goal:  [Please select goal from dropdown menu below]

Goal #2 Beautify & Enhance the Quality of Place


Comprehensive Plan Element (s)
: [Please select the Plan element(s) and Goal # from below]
Economic Development Choose an item.
Environment & Resource Protection Choose an item.
Land Use Choose an item.
Neighborhoods & Housing Choose an item.
Parks, Public Spaces & Facilities Choose an item.
Transportation Choose an item.

Not Applicable

Master Plan
: [Please select the corresponding Master Plan from the dropdown menu below (if applicable)]
Choose an item.

 

Background Information:

The City of San Marcos is authorized by the Local Government Code, Chapter 271, to participate in cooperative purchasing programs.  The Education Service Center (ESC) Region 19 Allied States Cooperative (ASC) has awarded contract #18-7280 for Playground/Park Systems, Installation and Related to T.F. Harper and Associates, LP, located in Austin, Texas.  This is to approve a contract with T.F. Harper and Associates, LP in the total amount of $1,251,516.

 

The purpose of this project is to replace the 25-year-old wooden Children’s Playscape with a modern rendition that will be an all-inclusive playground for children of all abilities.  It will include areas for children ages 2 through 5 and ages 5 through 12 with custom design features that bring a unique local flair to the play area designed by Leathers and Associates.  This project will be contained within the current footprint of the current playscape.

 

The original playscape was constructed in November 1992 through a community build process with City funds and both monetary and physical donations.  The existing playscape has served thousands of San Marcos and Central Texas children over the last 25 years.  In 2013, due to the deteriorating condition and ADA accessibility, the playscape was added to the 10-year CIP with design to be funded in 2016 and construction to occur in 2017.  In February 2017, City Council authorized the selection of Leathers and Associates for the design of the Children’s Playscape Renovation.

 

The following schedule is anticipated for construction:

                     January 2018 - Deconstruction of existing playscape

                     February 2018 - Begin construction (mid to late February)

                     April 2018 - Complete construction (end of April)

 

Council Committee, Board/Commission Action: Click or tap here to enter text.

Alternatives:

 