File #: Res. 2020-108R    Version: 1 Name:
Type: Resolution Status: Individual Consideration
File created: 5/4/2020 In control: City Council
On agenda: 6/2/2020 Final action:
Title: Consider approval of Resolution 2020-108R, approving a Change in Service to the engineering services agreement with Lockwood, Andrews & Newnam, Inc. relating to the Purgatory Creek Improvements Project in the estimated amount of $174,734.00 for a total contract price of $2,336,948.00; authorizing the City Manager or his designee to execute the appropriate purchasing documents to implement the change in service; and declaring an effective date.
Attachments: 1. Resolution - Change in Service Lockwood, Andrews & Newman - .pdf, 2. 200427_LAN_PURGCRKPH2_PermittingProposal.pdf, 3. USACE Phase 2 Area Project Location Map.pdf, 4. LAN Authorization of Change in Service.pdf
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
AGENDA CAPTION:
Title
Consider approval of Resolution 2020-108R, approving a Change in Service to the engineering services agreement with Lockwood, Andrews & Newnam, Inc. relating to the Purgatory Creek Improvements Project in the estimated amount of $174,734.00 for a total contract price of $2,336,948.00; authorizing the City Manager or his designee to execute the appropriate purchasing documents to implement the change in service; and declaring an effective date.

Body
Meeting date: June 2, 2020

Department: CIP / Engineering, Director, Laurie Moyer (by Lynda Williams, Purchasing Manager)

Amount & Source of Funding
Funds Required: $174,734
Account Number: C679
Funds Available: $319,800
Account Name: Purgatory Creek Improvements Phase 1

Fiscal Note:
Prior Council Action: December 3, 2019: Awarded professional engineering contract 218-307 to Lockwood, Andrews & Newnam, Inc. for an estimated amount of $1,694,774 to prepare 30 Percent Design Phase Engineering Services for the Purgatory Creek Improvements project. On June 5, 2018, LAN, Inc. was awarded $467,440 to conduct preliminary engineering.

City Council Strategic Initiative: [Please select from the dropdown menu below]
Multi Modal Transportation
Choose an item.
Choose an item.

Comprehensive Plan Element (s): [Please select the Plan element(s) and Goal # from dropdown menu below]
? Economic Development - Choose an item.
? Environment & Resource Protection - Choose an item.
? Land Use - Choose an item.
? Neighborhoods & Housing - Choose an item.
? Parks, Public Spaces & Facilities - Choose an item.
? Transportation - Choose an item.
? Core Services
? Not Applicable

Master Plan: [Please select the corresponding Master Plan from the dropdown menu below (if applicable)]
Choose an item.


Background Information:
The objective of the Purgatory Creek Improvement project is to reduce flooding along Purgatory from the San Marcos River to the discharge from the NRCS Flood Control Dam #5 at Wonder World...

Click here for full text