Legislation Details

File #: Res. 2022-153R    Version: 1 Name:
Type: Resolution Status: Individual Consideration
File created: 5/19/2022 In control: City Council
On agenda: 8/2/2022 Final action:
Title: Consider approval of Resolution 2022-153R, authorizing a Change in Service to the agreement with Garver, LLC relating to the San Marcos Regional Airport Taxiway Engineering Project to advance the project to the construction phase in the amount of $372,100.00; authorizing the City Manager or her designee to execute the appropriate documents to implement the Change in Service on behalf of the City; and declaring an effective date.
Attachments: 1. Resolution, 2. HYI Taxiway C Improvements-Authorization of CIS-Garver executed.pdf, 3. Taxiway Charlie Location Map.pdf
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
AGENDA CAPTION:
Title
Consider approval of Resolution 2022-153R, authorizing a Change in Service to the agreement with Garver, LLC relating to the San Marcos Regional Airport Taxiway Engineering Project to advance the project to the construction phase in the amount of $372,100.00; authorizing the City Manager or her designee to execute the appropriate documents to implement the Change in Service on behalf of the City; and declaring an effective date.
Body
Meeting date: August 2, 2022

Department: Engineering and CIP, Shaun Condor, Interim Director (by Lynda Williams, Purchasing & Contracting Manager)

Amount & Source of Funding
Funds Required: $372,100
Account Number: C524. GL: 50036383-70200
Funds Available: $930,179.63
Account Name: Airport Taxiway System, Ramp Rehab

Fiscal Note:
Prior Council Action: 2018-186 - Professional Services Agreement with Garver LLC

City Council Strategic Initiative: [Please select from the dropdown menu below]
N/A
Choose an item.
Choose an item.

Comprehensive Plan Element (s): [Please select the Plan element(s) and Goal # from dropdown menu below]
? Economic Development - Promote & Support Potential of San Marcos Regional Airport
? Environment & Resource Protection - Choose an item.
? Land Use - Choose an item.
? Neighborhoods & Housing - Choose an item.
? Parks, Public Spaces & Facilities - Choose an item.
? Transportation - Choose an item.
? Core Services
? Not Applicable

Master Plan: [Please select the corresponding Master Plan from the dropdown menu below (if applicable)]
Airport Master Plan


Background Information:
In October of 2018 the city commenced design with Garver LLC (218-404) of the replacement/repair of the airports two main taxiways (Alpha and Charlie) due to their deteriorated condition. The FAA (through TxDOT Aviation) confirmed that funding for construction of the taxiways will be in two separate years with Taxiway Charlie this fiscal year and Taxiway Alpha in FY23.

This change in service to the...

Click here for full text