AGENDA CAPTION:
Title
Consider approval of Resolution 2024-156R, approving the award of a construction contract to Aaron Concrete Contractors, LLC., for the East Aquarena Springs Drive Reconstruction Project in the estimated amount of $1,169,208.75; authorizing the City Manager, or her designee, to execute the contract on behalf of the city; and declaring an effective date.
Body
Meeting date: August 20, 2024
Department: Engineering & CIP
Amount & Source of Funding
Funds Required: $1,169,208.75
Account Number: C582
Funds Available: $1,339,371.81
Project Number
Fund
Phase
GL Account
Amount
C582: E. Aquarena Springs Dr Reconstruction
General
CO22A/CO24A
50092483/90 70200
$867,073
Drainage
CO20A/CO21A/CO24A
51092470/78/90 70200
$302,136
Account Name: E. Aquarena Springs Drive Reconstruction.
Fiscal Note:
Prior Council Action: NA
City Council Strategic Initiative: [Please select from the dropdown menu below]
Choose an item.
Choose an item.
Choose an item.
Comprehensive Plan Element (s): [Please select the Plan element(s) and Goal # from dropdown menu below]
? Economic Development - Choose an item.
? Environment & Resource Protection - Choose an item.
? Land Use - Choose an item.
? Neighborhoods & Housing - Choose an item.
? Parks, Public Spaces & Facilities - Choose an item.
? Transportation - Multimodal transportaion network to improve accessibility and mobility, minimize congestion and reduce pollution
? Core Services
? Not Applicable
Master Plan: [Please select the corresponding Master Plan from the dropdown menu below (if applicable)]
Transportation Master Plan
Background Information:
A total of 2 bids were received for the E. Aquarena Springs Drive Reconstruction project on June 20th, 2024. The low bidder for this project is Aaron Concrete Contractors, LLC, with a bid amount of $1,169,208.75.
E. Aquarena Springs Drive Reconstruction project will include the construction of asphalt pavement, curb and gutter, sidewalk, curb ramps, and storm...
Click here for full text