AGENDA CAPTION:
Title
Consider approval of Resolution 2026-106R, approving Change Order No. 3 to the contract with Guerra Underground, LLC for the Dunbar Water and Wastewater Improvement Project for asphalt paving repair upgrades in the amount of $476,665.00 for a total contract price of $7,397,390.07: authorizing the City Manager, or her designee, to execute the Change Order on behalf of the city; and declaring an effective date.
Body
Meeting date: July 7, 2026
Department: Engineering/CIP
Amount & Source of Funding
Funds Required: $476,665.00
Account or Project Number (C = CIP funds): C704
Funds Available: Yes
Account Name: Dunbar Utility Imps
Fiscal Note:
Prior Council Action: Res No. 2020-119R, Award of Preliminary Engineering Contract, Res No. 2021-190R, Award of Final Design Contract, RES 2024-127R, Construction Contract
City Council Strategic Initiative: [Please select from the dropdown menu below]
Public Safety, Core Services & Fiscal Excellence
Choose an item.
Choose an item.
Comprehensive Plan Element (s): [Please select the Plan element(s) and Goal # from dropdown menu below]
? Arts and Culture - Choose an item.
? Economic Development - Choose an item.
? Environment & Resource Protection - Choose an item.
? Housing + Neighborhoods - Choose an item.
? Land Use + Community Design and Character - Choose an item.
? Parks & Public Spaces + Health, Safety & Wellness - Choose an item.
? Transportation - Choose an item.
? Core Services
? Not Applicable
Master Plan: [Please select the corresponding Master Plan from the dropdown menu below (if applicable)]
Choose an item.
Background Information:
The attached Change Order #3 for $476,665.00 to Construction Contract 223-277 with Guerra Underground, LLC will upgrade the paving repair from a typical trench repair to a full width (curb to curb) asphalt paving repair to the entire project. This effort is associated with the Dunbar Water and Wastewater Improvement Project and the total contract amou...