AGENDA CAPTION:
Title
Consider approval of Resolution 2025-158R, approving Change Order No. 1 to the contract with Guerra Underground, LLC for the Dunbar Water and Wastewater Improvement Project in the amount of $604,034.24 for a total contract price of $6,889,344.96; authorizing the City Manager, or her designee, to execute the change order on behalf of the city; and declaring an effective date.
Body
Meeting date: September 2, 2025
Department: Engineering/CIP Department - Shaun Condor, Director
Amount & Source of Funding
Funds Required: $604,034.24
Account Number: C618-Drainage ($305,848.03), C704-WWW ($298,186.21)
Funds Available: Yes
Account Name: Various Drainage, Dunbar Utility Imps
Fiscal Note:
Prior Council Action: RES 2018-221R-Various Drainage Design Contract, RES 2024-162R-Various Drainage Rejection of Bids, RES 2024-127R-Dunbar Water and Wastewater Improvements Construction Contract
City Council Strategic Initiative: [Please select from the dropdown menu below]
Public Safety, Core Services & Fiscal Excellence
Choose an item.
Choose an item.
Comprehensive Plan Element (s): [Please select the Plan element(s) and Goal # from dropdown menu below]
? Economic Development - Choose an item.
? Environment & Resource Protection - Choose an item.
? Land Use - Choose an item.
? Neighborhoods & Housing - Choose an item.
? Parks, Public Spaces & Facilities - Choose an item.
? Transportation - Choose an item.
? Core Services
? Not Applicable
Master Plan: [Please select the corresponding Master Plan from the dropdown menu below (if applicable)]
Stormwater Master Plan
Background Information:
The attached Change Order to contract 223-277 with Guerra Underground LLC for the Dunbar Water and Wastewater Improvement Project in the amount of $604,034.24, will add additional scope to the Dunbar project associated with two (2) different tasks. One task will address scope changes on the Dunbar project and the second task will add scope associated with the...