File #: Res. 2014-145R    Version: 1 Name:
Type: Resolution Status: Individual Consideration
File created: 9/19/2014 In control: City Council
On agenda: 10/21/2014 Final action:
Title: Consider approval of Resolution 2014-145R approving a Reimbursement Agreement with Enterprise Texas Pipeline, L.L.C. providing for the City to reimburse the costs incurred to relocate gas pipeline facilities in the estimated amount of $785,000.00 in connection with the Willow Springs Creek Drainage Improvements Project; authorizing the City Manager to execute said agreement; and declaring an effective date.
Attachments: 1. Resolution, 2. A13323 City of San Marcos - Exec Reimb Agrmt Rev 1b, 3. Revised Cost Estimate 9-23-14, 4. Enterprise Construction Drawings, 5. Enterrise Gas Main Location Map, 6. Willow Springs Channel LocoMap
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
AGENDA CAPTION:
Title
Consider approval of Resolution 2014-145R approving a Reimbursement Agreement with Enterprise Texas Pipeline, L.L.C. providing for the City to reimburse the costs incurred to relocate gas pipeline facilities in the estimated amount of $785,000.00 in connection with the Willow Springs Creek Drainage Improvements Project; authorizing the City Manager to execute said agreement; and declaring an effective date.

Body
Meeting date: October 21, 2014

Department: Engineering and Capital Improvements

Funds Required: $785,000.00
Account Number: 616.562.73128, FY 2015 Project
Funds Available: $2,239,344.00, $850,000
Account Name: Victory Gardens Improv, Victory Gardens Subdivision Ph I, North Section


CITY COUNCIL GOAL:
Big Picture Infrastructure, Protect the San Marcos River

BACKGROUND:
This reimbursement agreement is with Enterprise Pipeline, LLC for the relocation of a high pressure gas line. The lowering of the gas line is required for wastewater and drainage channel improvements proposed with the City's Willow Springs Creek Improvement project. This project is associated with the overall Victory Gardens Neighborhood Project and will remove approximately 60 structures from the current 100-yr floodplain after the proposed drainage improvements are complete. This project will also replace an existing wastewater line as recommended by the Wastewater Master Plan.

A previous reimbursement agreement with Enterprise was approved by City Council in November 2013 based upon a preliminary cost estimate. After final design and construction bids were obtained, the estimated cost of the gas line relocation increased to $785,000. The revised cost from Enterprise has been validated by the City's design consultant. Bowman Engineering. The City also attempted to obtain cost participation from Enterprise, but it was unsuccessful.

Staff has evaluated whether it would be better for the City to revise the City project to a...