File #: Res. 2021-174R    Version: 1 Name:
Type: Resolution Status: Individual Consideration
File created: 7/29/2021 In control: City Council
On agenda: 9/7/2021 Final action:
Title: Consider approval of Resolution 2021-174R, approving several Change Orders to the construction contract with Trimbuilt Construction Inc. relating to the San Marcos Police Department Building Renovations and Additions Project in the amount of $153,621.48; authorizing the City Manager or his designee to execute the appropriate documents relating to the Change Orders on behalf of the City; and declaring an effective date.
Attachments: 1. Resolution, 2. 220-149 CO6 $7,542.54 06-15-21 (Executed), 3. 220-149 CO7 $10,844.52 06.15.21 (Executed), 4. 220-149 CO 8 $49,510.88 07.21.21 (Executed), 5. 220-149 CO#9 $11,526.71 07.23.21 (executed), 6. 220-149 CO#10 $23,764.48 07.27.21 (executed), 7. 220-149 CO#11 $34,639.54 08.04.21 (executed), 8. 220-149 CO#12 $15,792.81 08.06.21(executed)
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
AGENDA CAPTION:
Title
Consider approval of Resolution 2021-174R, approving several Change Orders to the construction contract with Trimbuilt Construction Inc. relating to the San Marcos Police Department Building Renovations and Additions Project in the amount of $153,621.48; authorizing the City Manager or his designee to execute the appropriate documents relating to the Change Orders on behalf of the City; and declaring an effective date.

Body
Meeting date: September 7, 2021

Department: Police Department - Chase Stapp, Director (by Lynda Williams, Purchasing Manager)

Amount & Source of Funding
Funds Required: $153,621.48
Account Number: 500361078-70200 (G608)
Funds Available: Click or tap here to enter text.
Account Name: GO Bond-Police Department Renovations

Fiscal Note:
Prior Council Action: May 2017, bond projects, including renovations and additions to the San Marcos Police Department was approved by voters. June 16, 2020 Resolution #2020-127R, Council approved a construction contract for renovations to the police department to Trimbuilt Construction, Inc. Resolution 2021-74R, Council approved an increase to the Owner's Contingency.

City Council Strategic Initiative: [Please select from the dropdown menu below]
Choose an item.
Choose an item.
Choose an item.

Comprehensive Plan Element (s): [Please select the Plan element(s) and Goal # from dropdown menu below]
? Economic Development - Choose an item.
? Environment & Resource Protection - Choose an item.
? Land Use - Choose an item.
? Neighborhoods & Housing - Choose an item.
? Parks, Public Spaces & Facilities - Choose an item.
? Transportation - Choose an item.
? Core Services
? Not Applicable

Master Plan: [Please select the corresponding Master Plan from the dropdown menu below (if applicable)]
Choose an item.


Background Information:
Significant renovations and additions to the police department began in July, 2020 by general contractor, Trimbuilt Construction, Inc. in the amount of...

Click here for full text