Title: Consider approval of Resolution 2026-18R, approving a Contract with Arguijo Corporation to provide for the Lift Station 24 Upgrades Project in the amount of $1,016,716.62; authorizing the City Manager, or her designee, to execute the contract on behalf of the city; and declaring an effective date.
Attachments: 1. Resolution, 2. LS 24 Upgrades Location Map, 3. LS 24 Recommendation of Award Letter
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
AGENDA CAPTION:
Title
Consider approval of Resolution 2026-18R, approving a Contract with Arguijo Corporation to provide for the Lift Station 24 Upgrades Project in the amount of $1,016,716.62; authorizing the City Manager, or her designee, to execute the contract on behalf of the city; and declaring an effective date.
Body
Meeting date: January 20, 2026

Department: Engineering and Capital Improvements, Shaun Condor, Director

Amount & Source of Funding
Funds Required: $ 1,016,716.62
Account Number: Project C571
Funds Available: Yes
Account Name: FM 1978 Water Reclamation Facility

Fiscal Note:
Prior Council Action: Resolution 2024-64R, On-Call Engineering Services Contract for Wastewater System Improvements and Planning

City Council Strategic Initiative: [Please select from the dropdown menu below]
Public Safety, Core Services & Fiscal Excellence
Choose an item.
Choose an item.

Comprehensive Plan Element (s): [Please select the Plan element(s) and Goal # from dropdown menu below]
? Economic Development - Choose an item.
? Environment & Resource Protection - Choose an item.
? Land Use - Choose an item.
? Neighborhoods & Housing - Choose an item.
? Parks, Public Spaces & Facilities - Choose an item.
? Transportation - Choose an item.
? Core Services
? Not Applicable

Master Plan: [Please select the corresponding Master Plan from the dropdown menu below (if applicable)]
Wastewater Master Plan


Background Information:
On November 20, 2025, two bids were received for the Lift Station 24 Upgrades Project IFB# 2025-122. Arguijo Corporation was the apparent low bidder with a total base bid of $1,016,716.62. Based on their qualifications and references, they appear to be qualified to perform the work on this project.
This project proposes to rehabilitate the lift station including pump replacement, installation of Variable Frequency Drive (VFD) pumps, electrical and instrumentation upgrades, wet well and valve vault rehabilitation, and installation of ...

Click here for full text