AGENDA CAPTION:
Title
Consider approval of Resolution 2015-70R, approving the award of a construction contract to Cox Commercial Construction, LLC for the Stagecoach Trail Widening Project in the total amount of $350,583.00 contingent upon the Contractor's timely submission of sufficient bonds and insurance in accordance with the City's construction contract documents for the project; authorizing the City Manager or his designee to execute all appropriate contract documents on behalf of the City and declaring an effective date.
Body
Meeting date: June 16, 2015
Department: Capital Improvements - Laurie Moyer, Director (By Cheryl Pantermuehl, Purchasing Manager)
Funds Required: $350,583.00
Account Number: 50036350.70200
Funds Available: $350,000 Dependent upon the approval of $285,000 being approved in the 2016 CIP ($65,000 will be paid by the San Marcos Independent School District)
Account Name: Stagecoach Widening
CITY COUNCIL GOAL:
BACKGROUND:
On June 10, 2015, the City received one (1) bid for the Stagecoach Trail Widening Project (IFB 215-195). The design engineer, Bill Gabler, P.E., of Bowman Consulting, Inc., has reviewed the bids and recommends awarding the contract to the low bidder, Cox Commercial Construction, located in Austin, Texas, in the amount of $350,583.
Due to increased traffic during school hours, an additional lane is needed to prevent the hindrance of through traffic. This project's timing is crucial and it must commence as soon as possible to prevent any traffic delays due to construction during the 2015/2016 school year.
The project scope includes: the widening of Stagecoach Trail to add a dedicated right turn lane approximately 1350 feet in length; improved drainage; inclusion of a bio-retention pond; and new traffic striping and signage.
Under an Interlocal agreement between SMCISD and the City approved in February 2014, the district will participate in the amount of $65,000 toward the cons...