Legislation Details

File #: Res. 2026-176R    Version: 1 Name:
Type: Resolution Status: Individual Consideration
File created: 9/9/2026 In control: City Council
On agenda: 10/7/2026 Final action:
Title: Consider approval of Resolution 2026-176R, approving Change Order No. 11 to the Surface Water Treatment Plant Improvements construction contract with Archer Western Construction, LLC, to install a new water quality sampling tap in the amount of $396,944.02, of which $169,892.04 is to be paid by the city and $227,051.98 is to be paid by Guadalupe-Blanco River Authority; authorizing the City Manager, or her designee, to execute the change order on behalf of the city; and declaring an effective date.
Attachments: 1. Resolution, 2. Change Order 11, 3. SWTP Improvements - Project Location, 4. Approved - San Marcos SWTP CT Study - Letter from TCEQ
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
AGENDA CAPTION:
Title
Consider approval of Resolution 2026-176R, approving Change Order No. 11 to the Surface Water Treatment Plant Improvements construction contract with Archer Western Construction, LLC, to install a new water quality sampling tap in the amount of $396,944.02, of which $169,892.04 is to be paid by the city and $227,051.98 is to be paid by Guadalupe-Blanco River Authority; authorizing the City Manager, or her designee, to execute the change order on behalf of the city; and declaring an effective date.

Body
Meeting date: October 7, 2026

Department: : Engineering/CIP, Shaun Condor, Director

Amount & Source of Funding
Funds Required: $396,944.02; Shared between COSM $169,892.04 & GBRA $227,051.98
Account or Project Number (C = CIP funds): C741
Funds Available: Yes
Account Name: ARWA Delivery Improvements

Fiscal Note:
Prior Council Action: R2021-101 Awarding Contract to Archer Western, 2022-156R for Change Order #2, 2023-14R for Change Order #4 & 2026-47R for Change Order #10

City Council Strategic Initiative: [Please select from the dropdown menu below]
Public Safety, Core Services & Fiscal Excellence
Choose an item.
Choose an item.

Comprehensive Plan Element (s): [Please select the Plan element(s) and Goal # from dropdown menu below]
N/A Arts and Culture - Choose an item.
N/A Economic Development - Choose an item.
N/A Environment & Resource Protection - Choose an item.
N/A Housing + Neighborhoods - Choose an item.
N/A Land Use + Community Design and Character - Choose an item.
N/A Parks & Public Spaces + Health, Safety & Wellness - Choose an item.
N/A Transportation - Choose an item.
Yes Core Services
N/A Not Applicable

Master Plan: [Please select the corresponding Master Plan from the dropdown menu below (if applicable)]
Water Master Plan


Background Information:
Staff is requesting approval of Change Order No. 11 to the Surface Water Treatment Plant (SWTP) Improvements Project, located at 91 Old Bastrop Highway, construct...

Click here for full text