AGENDA CAPTION:
Title
Consider approval of Resolution 2025-174R, approving a change order to the contract with Austin Underground, Inc. for the Sessom Drainage and Street Improvements Project to add the construction of Gateway Monument Signs in the amount of $458,111.00; authorizing the City Manager, or her designee, to execute the change order on behalf of the city; and declaring an effective date.
Body
Meeting date: September 16, 2025
Department: Engineering and CIP
Amount & Source of Funding
Funds Required: $458,111.00
Account Number: C419-General ($458,111.00)
Funds Available: Yes
Account Name: C419-Sessom Drainage & Street Improvements
Fiscal Note:
Prior Council Action: 2022-62R, Sessom Dr Drainage and Street Imps Construction Contract Award;2024-13R, Change Order No 5 to add Hopkins/Guadalupe Intersection Improvements Construction.
City Council Strategic Initiative: [Please select from the dropdown menu below]
Economic Vitality
Quality of Life & Sense of Place
Choose an item.
Comprehensive Plan Element (s): [Please select the Plan element(s) and Goal # from dropdown menu below]
? Economic Development - Choose an item.
? Environment & Resource Protection - Choose an item.
? Land Use - Choose an item.
? Neighborhoods & Housing - Choose an item.
? Parks, Public Spaces & Facilities - Choose an item.
? Transportation - Choose an item.
? Core Services
? Not Applicable
Master Plan: [Please select the corresponding Master Plan from the dropdown menu below (if applicable)]
Arts Master Plan
Background Information:
The attached Change Order to Contract 221-183 with Austin Underground, Inc., for the Sessom Dr. Drainage and Roadway Improvements Project, in the amount of $458,111.00, will add the Gateway Monument Signs Construction to the existing contract.
The City of San Marcos issued an Invitation for Bids (IFB 2025-089) for the Gateway Monument Signs Along IH-35 construction project on March 9th, 2025. The bids closed on April 10th, 2025, and the...
Click here for full text