Title: Consider approval of Resolution 2022-67R authorizing a Change Order to the construction contract with Myers Concrete Construction, LP, relating to the San Marcos Downtown Accessible Pedestrian Traffic Signal Improvements Project to decrease the contract price in the amount of $125,994.80; authorizing the City Manager or her designee to execute the Change Order on behalf of the City; and declaring an effective date.
Attachments: 1. Resolution, 2. 221-113 Change Order k-signed.pdf
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

AGENDA CAPTION:

Title

Consider approval of Resolution 2022-67R authorizing a Change Order to the construction contract with Myers Concrete Construction, LP, relating to the San Marcos Downtown Accessible Pedestrian Traffic Signal Improvements Project to decrease the contract price in the amount of $125,994.80; authorizing the City Manager or her designee to execute the Change Order on behalf of the City; and declaring an effective date.

 

Body

Meeting date:  April 5, 2022

 

Department:  Transportation, Public Works - Sabas Avila, Director (by Lynda Williams, Purchasing Manager)

 

Amount & Source of Funding
Funds Required:
  $0.00

Account Number:  50036712-70300

Funds Available:  Click or tap here to enter text.

Account Name:  TxDOT Grant and City Funds

 

Fiscal Note:
Prior Council Action: Resolution 2022-13R approved January 18, 2022 - awarding construction contract to Myers Concrete Construction LP, for the San Marcos Downtown Accessible Pedestrian Traffic Signal Improvements project in the total amount of $368,052.04

City Council Strategic Initiative:  [Please select from the dropdown menu below]

Community Safety

Choose an item.

Choose an item.

 

Comprehensive Plan Element (s): [Please select the Plan element(s) and Goal # from dropdown menu below]
Economic Development - Choose an item.
Environment & Resource Protection - Choose an item.
Land Use - Choose an item.
Neighborhoods & Housing - Choose an item.
Parks, Public Spaces & Facilities - Choose an item.
Transportation - Safe, Well coordinated transportation system implemented in an environmentally sensitive manner

Core Services

Not Applicable

Master Plan
: [Please select the corresponding Master Plan from the dropdown menu below (if applicable)]
Transportation Master Plan

 

Background Information:

On January 18, 2022, the San Marcos Downtown Accessible Pedestrian Traffic Signal Improvements project was awarded to Myers Concrete Construction LP, in the amount of $368,052.04. The project includes concrete services and conduit installation, and updates of existing non-ADA compliant traffic signals at nine intersections in the downtown district with ADA-compliant sidewalk ramps, audible pedestrian push buttons, and countdown pedestrian signal heads to improve pedestrian mobility for all ages and abilities.

 

Following the City’s award, TxDOT notified the City that TxDOT contractors will complete (at TxDOT cost) the same ADA-compliant improvements proposed by the City at three intersections.  The following three intersection: Guadalupe/Hopkins; Guadalupe/San Antonio; and Guadalupe/MLK that were part of the City’s original project will be completed by TxDOT’s SL 82 ADA Improvement Project (STP 20209967 / 0914-00-446).

 

This change order will remove these three intersections from the City project for a cost reduction in work of $125,994.80 which results in a 34.2% decrease to the original contract amount.  The contractor was notified of the deletion of the three intersections and has agreed to the deductive change.

 

Council Committee, Board/Commission Action:
Click or tap here to enter text.

Alternatives:

Click or tap here to enter text.


Recommendation: 

Staff recommends approval of the deductive change order in the amount of $125,994.80.