File #: ID#16-08    Version: 1 Name:
Type: Action Item Status: Individual Consideration
File created: 12/23/2015 In control: City Council
On agenda: 2/2/2016 Final action:
Title: Consider approval, by motion, of Change in Service No. 4 Halff Associates, Inc. for Engineering Services for the Old RR 12 Bike/Ped and Widening Project in a not to exceed amount of $294,170.00.
Attachments: 1. RR12-LocationMap, 2. Halff CIS 4 Pending
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

AGENDA CAPTION:

Title

Consider approval, by motion, of Change in Service No. 4 Halff Associates, Inc. for Engineering Services for the Old RR 12 Bike/Ped and Widening Project in a not to exceed amount of $294,170.00.

 

Body

Meeting date:  February 2, 2016

 

Department:  Engineering and Capital Improvements

 

Funds Required:  $294,170

Account Number:  C646

Funds Available:  $295,000

Account Name:  Old RR 12 Bike Ped Widening

 

CITY COUNCIL GOALMaintain and improve the City’s infrastructure.

 

COMPREHENSIVE PLAN ELEMENT(s):

Land Use

Goal 1 Direct growth, compatible with surrounding uses

LUG105 Align infrastructure plans to achieve preferred scenario

 

Transportation

Goal 2 A multimodal transportation network to improve accessibility, mobility, minimize congestion and reduce pollution

TG203 Obtain "Bicycle Friendly Community" Designation

TG205 Develop and implement a complete streets policy for coordination with other transportation related entities to properly integrate all modes of transportation into the transportation network

TG207 Integrate the transportation system by coordinating with all related public entities, including, but not limited to CAMPO, the counties, TxDOT, the university, and the rail district

 

BACKGROUND

The scope for this change in services with Halff Associates, Inc. was negotiated and is being submitted for Council approval for a not to exceed amount of $294,170.00.  This Change In Service # 4 increases the contract to finalize the design plans and provide engineering services during construction. 

 

In late 2014 the City Council approved the cancellation of $99,000 in CAMPO funding and delayed the project due to construction conflicts with the N. LBJ and to allow more time to address design issues.  Over the last year staff has surveyed residents about the project scope, performed additional drainage investigations, continued to work with TXDOT on the ROW transfer and have identified additional beautification aspects to add to the project. 

 

 

This change in service will include:

 

                     Drainage

o                     Sara Street Drainage included

o                     Revise calculations based upon revised cross section.

                     Water

o                     8” will be increased to a 12”

o                     Add 6” to 8” replacement on Sara street to accommodate drainage improvements

o                     Location will be moved into the street to allow for smoother construction

                     Wastewater

o                     Add replacement from Coers Street due to deteriorating condition

o                     Add replacement on Sara street to accommodate drainage revision and deteriorating condition

                     Sidewalk

o                     Old RR 12 between Craddock and Hughson (Retreat Side) - Increase sidewalk size from 6’ to 10’ and relocate into sidewalk easement

                     Beautification

o                     Add additional landscaping and irrigation to the plans

o                     Add decorative crosswalk to the project; where feasible

o                     Replace concrete rip rap with decorative retaining walls; where feasible

                     Driveways

o                     Investigate alternative design options for addressing steep driveways

                     Traffic Calming

o                     Provide documentation required to temporarily reduce the speed during construction from 40 MPH to 30 MPH.

o                     Add traffic feed-back signs to the project.

                     TCEQ

o                     Additional support needed for coordination with TCEQ and receiving approval for water quality features to be installed

 

The current cost estimate of $3.6 Million is expected to increase to approximately $4.5-5.0 Million with these revisions.  Construction is expected to start in the winter of 2018.

 

Staff recommends approval of this change in service.