Consider approval of Resolution 2026-52R, approving the reallocation of $457,516.41, from existing project contingency funds under the contract with CH2M HILL (Jacobs) for the San Marcos Wastewater Treatment Plant Miscellaneous Capital Improvements Project, to pay for the removal and replacement of structural steel elements at Clarifier No. 401 and the installation of the new hydraulic drive; authorizing the City Manager, or her designee, to execute the contingency reallocation on behalf of the city, and declaring an effective date.
Body
Meeting date: April 7, 2026
Department: W/WW
Amount & Source of Funding
Funds Required: 457,516.41
Account or Project Number (C = CIP funds): C727
Funds Available: Yes
Account Name: C727
Fiscal Note:
Prior Council Action: Debt funded in 2021; Res. 2005-012; Res. 2005-105R; Res. 2011-38R; Res. 2015-114R; Res. 2020-244R; Res. 2022-204R; Res. 2024-103R.
City Council Strategic Initiative: [Please select from the dropdown menu below]
Public Safety, Core Services & Fiscal Excellence
Choose an item.
Choose an item.
Comprehensive Plan Element (s): [Please select the Plan element(s) and Goal # from dropdown menu below]
☐ Arts and Culture - Choose an item.
☐ Economic Development - Choose an item.
☐ Environment & Resource Protection - Choose an item.
☐ Housing + Neighborhoods - Choose an item.
☐ Land Use + Community Design and Character - Choose an item.
☐ Parks & Public Spaces + Health, Safety & Wellness - Choose an item.
☐ Transportation - Choose an item.
☒ Core Services
☐ Not Applicable
Master Plan: [Please select the corresponding Master Plan from the dropdown menu below (if applicable)]
Choose an item.
Background Information:
Contingency Reallocation for the San Marcos Wastewater Treatment Plant Miscellaneous Capital Improvements Project, submitted by CH2M HILL (Jacobs) to the City of San Marcos. During inspections in late 2025, severe corrosion was discovered in the structural support system of Clarifier 401, requiring full removal and replacement before installation of a new hydraulic drive. A specialized contractor, CopperState, assessed the clarifier and provided a cost proposal for replacement of structural steel components and installation of new equipment. The total contingency reallocation requested is $457,516.41, covered entirely by existing project contingency funds, reducing the remaining contingency to $32,375.49 and extending project completion to October 15, 2026.
Council Committee, Board/Commission Action:
Click or tap here to enter text.
Alternatives:
Click or tap here to enter text.
Recommendation:
Staff Recommends Approval