Title: Consider approval of Resolution 2024-58R, approving an agreement with Kimley Horn and Associates, Inc., for the provision of professional engineering services for the Rattler Road Waterline Extension Project for $147,009.10; authorizing the City Manager, or her designee, to execute the agreement on behalf of the city; and declaring an effective date.
Attachments: 1. Resolution, 2. Location Map, 3. 20240213-Rattler Road Waterline Extension- Proposal-V1_
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

AGENDA CAPTION:

Title

Consider approval of Resolution 2024-58R, approving an agreement with Kimley Horn and Associates, Inc., for the provision of professional engineering services for the Rattler Road Waterline Extension Project for $147,009.10; authorizing the City Manager, or her designee, to execute the agreement on behalf of the city; and declaring an effective date.

Body

Meeting date:  April 16, 2024

 

Department:  Engineering/CIP, Shaun Condor, Director

 

Amount & Source of Funding
Funds Required:
  $147,009.10

Account Number:  C613-WWWIF 52044363-70200

Funds Available:  $150,000.00

Account Name:  Rattler Road Waterline Extension

 

Fiscal Note:
Prior Council Action: N/A

City Council Strategic Initiative:  [Please select from the dropdown menu below]

Public Safety, Core Services & Fiscal Excellence

Choose an item.

Choose an item.

 

Comprehensive Plan Element (s): [Please select the Plan element(s) and Goal # from dropdown menu below]
Economic Development - Choose an item.
Environment & Resource Protection -
Land Use - Choose an item.
Neighborhoods & Housing - Choose an item.
Parks, Public Spaces & Facilities - Choose an item.
Transportation - Choose an item.

Core Services

Not Applicable

Master Plan
: [Please select the corresponding Master Plan from the dropdown menu below (if applicable)]
Water Master Plan


Background Information:

The attached Professional Services Agreement for $147,009.10 with Kimley Horn and Associates, Inc. will provide engineering design and bid phase services for the City of San Marcos related to the Rattler Road Waterline Extension project.

 

The scope of work includes the installation of approximately 2,500 LF of 12” waterline from Old Bastrop Road to a point along Rattler Road 1,000 feet west of Highway 123.  This will complete a water main loop to provide a second feed to the Cottonwood Water Tank per the Water Master Plan.  Currently, the tank is only served by one feed.  Not having the ability to feed from multiple directions can become an issue if breaks or shutoffs occur on Highway 123.

 

Preliminary construction cost is estimated at $700,000 and scheduled to start in 2026.

 

Council Committee, Board/Commission Action:
Click or tap here to enter text.

Alternatives:

Click or tap here to enter text.


Recommendation: 

Staff recommends approval of this agreement.