AGENDA CAPTION:
Title
Consider approval of Resolution 2026-134R, authorizing a revised request for reimbursement from the Texas Department of Transportation from the original request of up to $130,000.00 to the revised request of up to $350,000.00 for the San Marcos Regional Airport Control Tower improvements; authorizing the City Manager, or her designee, to execute all contracts and agreements necessary to obtain such reimbursement and to execute a Designation of Sponsor’s Authorized Representative on behalf of the city; and declaring an effective date.
Body
Meeting date: August 18, 2026
Department: Engineering and CIP, Director Shaun Condor
Amount & Source of Funding
Funds Required: $0.00
Account or Project Number (C = CIP funds): C25
Funds Available: Yes
Account Name: Airport Control Tower
Fiscal Note:
Prior Council Action: None
City Council Strategic Initiative: [Please select from the dropdown menu below]
Public Safety, Core Services & Fiscal Excellence
Choose an item.
Choose an item.
Comprehensive Plan Element (s): [Please select the Plan element(s) and Goal # from dropdown menu below]
☐ Arts and Culture - Choose an item.
☐ Economic Development - Choose an item.
☐ Environment & Resource Protection - Choose an item.
☐ Housing + Neighborhoods - Choose an item.
☐ Land Use + Community Design and Character - Choose an item.
☐ Parks & Public Spaces + Health, Safety & Wellness - Choose an item.
☐ Transportation - Choose an item.
☒ Core Services
☐ Not Applicable
Master Plan: [Please select the corresponding Master Plan from the dropdown menu below (if applicable)]
Airport Master Plan
Background Information:
The need for improvements to the airport control tower was identified in the 2025 Airport Master Plan. The City tasked consulting firm Garver to produce an Assessment Report about the existing condition of the airport control tower, and to recommend specific improvements. The City used the Assessment Report to make a request to Texas Department of Transportation (TXDOT) Aviation for Federal Aviation Administration (FAA) grant funding to implement the recommended improvements.
The FAA announced an award not to exceed the revised amount of $130,000 in May 2026 for the cost of constructing the recommended HVAC, Electrical, and Plumbing improvements for the airport control tower, as per the Assessment Report. The scope of this work does not require design, environmental, or survey services since it’s maintenance replacement work. The scope of this work will be assigned to vendors from Purchasing Cooperatives that are complaint with the federal conditions of the FAA grant.
On July 20, 2026, TXDOT revised the award from $130,000 to $350,000. Therefore, the scope of the project was increased as per the recommendations of the Assessment Report.
TxDOT Aviation requires a updated resolution from the local sponsor requesting financial assistance up to $350,000, which will be through reimbursement. Additionally, the City Manager must document, through designation, the City’s project manager.
The estimated cost of the project is revised from $130,000 to $350,000, unless subsequently authorized. The City will be responsible for 0% of the actual cost and will be reimbursed for 100% of the actual cost up to $350,000. Any cost above the TXDOT grant will be 100% covered by the City.
Construction is anticipated to begin in September 2026 and conclude by March 2027.
Council Committee, Board/Commission Action:
Click or tap here to enter text.
Alternatives:
Click or tap here to enter text.
Recommendation:
Staff recommends approval