Legislation Details

File #: Res. 2022-156R    Version: 1 Name:
Type: Resolution Status: Individual Consideration
File created: 7/5/2022 In control: City Council
On agenda: 8/2/2022 Final action:
Title: Consider approval of Resolution 2022-156R, approving a Change Order to the Surface Water Treatment Plant Improvements Construction Contract requested by the Guadalupe-Blanco River Authority in the total amount of $266,893.94 with the City's portion being $52,667.82 to upgrade select line items; authorizing the City Manager or her designee to execute the appropriate documents relating to the Change Order on behalf of the City; and declaring an effective date.
Attachments: 1. Resolution, 2. 2022-06-30_RFP No. 2_Upgrade to Aluminum Conduit JRG.pdf, 3. 2022-06-30_RFP No. 3_Upgrade Generator Sound Attenuation JRG.pdf, 4. Change Order 2 Signed_PENDING.pdf, 5. SWTP Improvements - Project Location Map.pdf
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

AGENDA CAPTION:

Title

Consider approval of Resolution 2022-156R, approving a Change Order to the Surface Water Treatment Plant Improvements Construction Contract requested by the Guadalupe-Blanco River Authority in the total amount of $266,893.94 with the City’s portion being $52,667.82 to upgrade select line items; authorizing the City Manager or her designee to execute the appropriate documents relating to the Change Order on behalf of the City; and declaring an effective date.

 

Body

Meeting date:  August 2, 2022

 

Department:  Engineering/CIP, Shaun Condor, Interim Director (by Lynda Williams, Purchasing & Contracting Manager)

 

Amount & Source of Funding
Funds Required:
  Total = $266,893.94; COSM - $52,667.82; GBRA - $204,167.63; ARWA - $10,058.49

Account Number:  C741

Funds Available:  Per ILA

Account Name:  ARWA Delivery Improvements

 

Fiscal Note:
Prior Council Action: Resolution #2022-24R, January 18, 2022

City Council Strategic Initiative:  [Please select from the dropdown menu below]

City Facilities - Improve City’s Infrastructure

Choose an item.

Choose an item.

 

Comprehensive Plan Element (s): [Please select the Plan element(s) and Goal # from dropdown menu below]
☐ Economic Development - Choose an item.
☐ Environment & Resource Protection - Choose an item.
☐ Land Use - Choose an item.
☐ Neighborhoods & Housing - Choose an item.
☒ Parks, Public Spaces & Facilities - Choose an item.
☐ Transportation - Choose an item.

☐ Core Services

☐ Not Applicable

Master Plan
: [Please select the corresponding Master Plan from the dropdown menu below (if applicable)]
Water Master Plan


Background Information:

In January 2022 the city awarded the construction contract of the Surface Water Treatment Plant (SWTP) Improvement’s project to Archer Western in the amount of $12,945,554.10.  The cost of this project is shared between the City of San Marcos, Alliance Regional Water Authority (ARWA) and the Guadalupe-Blanco River Authority (GBRA).  The City is responsible for $5,863,444.05 of this original award amount. The improvements at the SWTP are needed to take delivery of the new ARWA water supply to the City. 

 

During the submittal review process, a few items were identified as outdated and it was decided to update them to the most current design standards.  Change Order 2, in the amount of $266,893.94, will upgrade these items.  The City is responsible for $52,667.82 of this amount. 

 

 

Council Committee, Board/Commission Action:
Click or tap here to enter text.

Alternatives:

Click or tap here to enter text.


Recommendation: 

Staff recommends approval of this change order