Legislation Details

File #: Res. 2026-211R    Version: 1 Name:
Type: Resolution Status: Individual Consideration
File created: 10/26/2026 In control: City Council
On agenda: 11/17/2026 Final action:
Title: Consider approval of Resolution 2026-211R, approving a Change in Service to the agreement with Burns & McDonnell Engineering Company, Inc. authorizing the next phase of Design-Build Services for the FM 1978 Water Reclamation Facility project, located at 548 Fleming Pass, in the estimated amount of $66,748,417.00; authorizing the City Manager, or her designee, to execute the Change in Service and to finalize any non-material revisions on behalf of the city; and declaring an effective date.
Attachments: 1. Resolution, 2. FM 1978 WRF Map, 3. B&McD CIS#3 FM 1978 WRF Ph. 2B
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

AGENDA CAPTION:

Title

Consider approval of Resolution 2026-211R, approving a Change in Service to the agreement with Burns & McDonnell Engineering Company, Inc. authorizing the next phase of Design-Build Services for the FM 1978 Water Reclamation Facility project, located at 548 Fleming Pass, in the estimated amount of $66,748,417.00; authorizing the City Manager, or her designee, to execute the Change in Service and to finalize any non-material revisions on behalf of the city; and declaring an effective date.

Body

Meeting date:  November 17, 2026

 

Department:  Engineering and Capital Improvements

 

Amount & Source of Funding
Funds Required:
  $66,748,417.00

Account or Project Number (C = CIP funds):  C571

Funds Available:  Yes

Account Name:  FM 1978 Water Reclamation Facility

 

Fiscal Note:
Prior Council Action: Res. 2024-78R Regional Wastewater Services and Facilities Cost Sharing Agreement and subsequent amendments; Res. 2025-125R Contract with Burns & McDonnell Engineering Company, Inc.; June 16, 2026 - Council Presentation Update; July 7, 2026 - Res. 2026-121R Change in Service to the agreement for Phase 2A

City Council Strategic Initiative:  [Please select from the dropdown menu below]

Public Safety, Core Services & Fiscal Excellence

Choose an item.

Choose an item.

 

Comprehensive Plan Element (s): [Please select the Plan element(s) and Goal # from dropdown menu below]

N/A Arts and Culture - Choose an item.
N/A Economic Development -
Choose an item.
N/A Environment & Resource Protection -
Choose an item.

N/A Housing + Neighborhoods - Choose an item.
N/A Land Use + Community Design and Character -
Choose an item.
N/A Parks & Public Spaces + Health, Safety & Wellness -
Choose an item.
N/A Transportation -
Choose an item.

Yes Core Services

N/A Not Applicable

Master Plan
: [Please select the corresponding Master Plan from the dropdown menu below (if applicable)]
Wastewater Master Plan


Background Information:

This resolution authorizes staff to proceed with an amount up to $66,748,417.00 the second planned contract price amendment to the progressive design-build agreement with Burns and McDonnell Engineering Company, Inc. for engineering services and construction for the FM 1978 Water Reclamation Facility project.

 

This second planned contract price amendment consists of the following scope of work elements for the two million gallons per day (2 MGD) water reclamation facility.

 

Phase 2B (Balance of Plant) Elements:

•                     Construction Phase Engineering Services

•                     Permitting Services

•                     Commissioning and Start-Up Services

•                     Site Work

•                     Electrical

•                     Yard Piping

•                     Cast-In-Place Concrete

•                     Structural Excavation

•                     Miscellaneous Metals

•                     Hoists

•                     Process Equipment Procurement

•                     Pre-Engineer Metal Buildings

•                     Interior Build-Out

•                     Paint and Coatings

•                     Plumbing

•                     HVAC

•                     Instrumentation and Controls

•                     Process Pipe and Equipment

•                     Fences and Gates

 

In May 2024, Council approved a cost sharing agreement with multiple developers to fund a new water reclamation facility in rapidly developing area in the southern part of San Marcos.  The new facility will allow the City to avoid multiple, small package plants throughout the area around and upstream of the San Marcos River.  The new facility is anticipated to treat 2 Million Gallons per Day (MGD) initially and be expandable to 8 MGD.  An alternative delivery method for design and construction of the wastewater treatment facility is required to meet the agreed schedule and provide price certainty in lieu of conventional design-bid-build method, typically employed by the city.

 

This project was identified as a priority in the 2025 Wastewater Master Plan to address treatment capacity issues anticipated due to growth in southern San Marcos.  Once FM 1978 Water Reclamation Facility is operational it will serve the immediate area and will allow the diversion of flows from the existing River Road Water Reclamation Facility to help defer some near-term capacity improvements needed there.

 

Construction is anticipated to begin on FM 1978 Water Reclamation Facility in November 2026  and complete in approximately two years.  This is the final planned amendment to the agreement.    

 

Council Committee, Board/Commission Action:
Click or tap here to enter text.

Alternatives:

Click or tap here to enter text.


Recommendation: 

Staff recommends approval of this item.