Consider approval of Resolution 2026-176R, approving Change Order No. 11 to the Surface Water Treatment Plant Improvements construction contract with Archer Western Construction, LLC, to install a new water quality sampling tap in the amount of $396,944.02, of which $169,892.04 is to be paid by the city and $227,051.98 is to be paid by Guadalupe-Blanco River Authority; authorizing the City Manager, or her designee, to execute the change order on behalf of the city; and declaring an effective date.
Body
Meeting date: October 7, 2026
Department: : Engineering/CIP, Shaun Condor, Director
Amount & Source of Funding
Funds Required: $396,944.02; Shared between COSM $169,892.04 & GBRA $227,051.98
Account or Project Number (C = CIP funds): C741
Funds Available: Yes
Account Name: ARWA Delivery Improvements
Fiscal Note:
Prior Council Action: R2021-101 Awarding Contract to Archer Western, 2022-156R for Change Order #2, 2023-14R for Change Order #4 & 2026-47R for Change Order #10
City Council Strategic Initiative: [Please select from the dropdown menu below]
Public Safety, Core Services & Fiscal Excellence
Choose an item.
Choose an item.
Comprehensive Plan Element (s): [Please select the Plan element(s) and Goal # from dropdown menu below]
N/A Arts and Culture - Choose an item.
N/A Economic Development - Choose an item.
N/A Environment & Resource Protection - Choose an item.
N/A Housing + Neighborhoods - Choose an item.
N/A Land Use + Community Design and Character - Choose an item.
N/A Parks & Public Spaces + Health, Safety & Wellness - Choose an item.
N/A Transportation - Choose an item.
Yes Core Services
N/A Not Applicable
Master Plan: [Please select the corresponding Master Plan from the dropdown menu below (if applicable)]
Water Master Plan
Background Information:
Staff is requesting approval of Change Order No. 11 to the Surface Water Treatment Plant (SWTP) Improvements Project, located at 91 Old Bastrop Highway, construction contract with Archer Western in the amount of $396,944.02, of which $169,892.04 is to be paid by the City and $227,051.98 is to be paid by Guadalupe-Blanco River Authority (GBRA), for the installation of a new sample tap at the SWTP.
The Texas Commission on Environmental Quality (TCEQ) reviewed the City’s SWTP Concentration Time (CT) Study and identified revisions necessary to the previously approved disinfection zones. As part of addressing TCEQ’s comments and demonstrating compliance with the Surface Water Treatment Rule, an additional sample tap is required at the SWTP to provide the appropriate monitoring location.
The sample tap installation was developed separately from the original SWTP Improvements project and was not included in the original construction contract. Plans for the sample tap installation have since been completed. The City currently has additional work scheduled at the SWTP under Change Order No. 10, previously approved by City Council, to reorient the flow meter and valve. To reduce costs and avoid a separate construction mobilization, staff proposes adding the sample tap installation to the existing contract so the work can be completed concurrently with the work associated with Change Order No. 10.
The proposed cost for Change Order No. 11 is $396,944.02, increasing the construction contract from $13,895,614.90 to $14,292,558.92. The proposed pricing is valid through October 9th, 2026. Construction is anticipated to begin upon completion of the work approved under Change Order No. 10 which is scheduled to begin in winter 2026.
Council Committee, Board/Commission Action:
Click or tap here to enter text.
Alternatives:
Click or tap here to enter text.
Recommendation:
Staff recommends approval of change order 11 in the amount of $396,944.02.