Skip to main content
File #: ID#21-546    Version: 1 Name:
Type: Presentation Status: Individual Consideration
File created: 6/28/2021 In control: City Council
On agenda: 8/17/2021 Final action:
Title: Receive a presentation from TxDOT staff on I-35 at SH 123 Improvements project.
Attachments: 1. SH 123_San Marcos City Council_v2_DHedits.pdf

AGENDA CAPTION:

Title

Receive a presentation from TxDOT staff on I-35 at SH 123 Improvements project.

Body

Meeting date:  August 3, 2021

 

Department:  Engineering & CIP

 

Amount & Source of Funding
Funds Required:
  NA

Account Number:  NA

Funds Available:  NA

Account Name:  NA

 

Fiscal Note:
Prior Council Action: Approval of Resolution # 2020-86R for AFA # 0016-03-114; SH 123 Drainage and Landscape Betterment.

City Council Strategic Initiative:  [Please select from the dropdown menu below]

Choose an item.

Choose an item.

Choose an item.

 

Comprehensive Plan Element (s): [Please select the Plan element(s) and Goal # from dropdown menu below]
Economic Development - Choose an item.
Environment & Resource Protection - Choose an item.
Land Use - Choose an item.
Neighborhoods & Housing - Choose an item.
Parks, Public Spaces & Facilities - Choose an item.
Transportation - Choose an item.

Core Services

Not Applicable

Master Plan
: [Please select the corresponding Master Plan from the dropdown menu below (if applicable)]
Choose an item.


Background Information:

Texas Department of Transportation’s (TxDOT) I-35 @ SH123 project consists of intersection improvements at I-35 and SH 123 and ramp reversals between SH 80 (Hopkins St) and RM 12 (Wonder World Dr). The purpose of this project is to improve safety and mobility.

 

Project Description:

 

                     Reconstruct and improve the SH 123 intersection

                     Reverse two ramps along the northbound frontage road between SH 80 and SH 123

                     Reverse one entrance ramp along the southbound frontage road between SH 80 and SH 123

                     Realign the existing southbound exit ramp to SH 123 (CM Allen Parkway)

                     Relocate the entrance ramp along the southbound frontage road from SH 80

                     Reconstruct portions of the northbound and southbound frontage roads, including improving bicycle and pedestrian accommodations

                     Reconstruct the frontage road bridges over Willow Springs Creek

                     Raise and reconstruct the northbound frontage road bridge over the San Marcos River

                     Widen the southbound frontage road bridge over the San Marcos River

                     Reconstruct the main lanes and bridge over SH 123

                     Add auxiliary lanes, or extended entrance/exit lanes, to the main lanes and frontage roads

 

Project Schedule:

 

Design Completion: anticipated mid 2021

Construction Letting: anticipated mid 2021

Construction Start: anticipated late 2021

Construction Completion: anticipated late 2025

 

The City is participating in IH35/SH123 Improvements project by contributing a fixed amount of funds ($5,822,990.22) towards the portion of the drainage and landscaping betterment.

 

Council Committee, Board/Commission Action:
NA

Alternatives:

NA


Recommendation: 

NA