File #: Res. 2021-32R    Version: 1 Name:
Type: Resolution Status: Individual Consideration
File created: 1/19/2021 In control: City Council
On agenda: 2/24/2021 Final action:
Title: Consider approval of Resolution 2021-32R, approving a Change in Service to the agreement with HDR Engineering, Inc., for various drainage improvement projects identified in the Stormwater Master Plan to add additional design and construction phase services in the estimated amount of $220,692.00; authorizing the City Manager or his designee to execute the appropriate documents to implement the Change in Service; and declaring an effective date.
Attachments: 1. Resolution, 2. COSM Various Drainage Design_Scope_200105, 3. Various Drainage Overall Map
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

AGENDA CAPTION:

Title

Consider approval of Resolution 2021-32R, approving a Change in Service to the agreement with HDR Engineering, Inc., for various drainage improvement projects identified in the Stormwater Master Plan to add additional design and construction phase services in the estimated amount of $220,692.00; authorizing the City Manager or his designee to execute the appropriate documents to implement the Change in Service; and declaring an effective date.

Body

Meeting date:  February 24, 2021

 

Department:  Engineering & CIP. Laurie Moyer, Director (by Lynda Williams, Purchasing Manager)

 

Amount & Source of Funding
Funds Required:
  $220,692

Account Number:  C618

Funds Available:  $1,268.578

Account Name:  Various Drainage Projects

 

Fiscal Note:
Prior Council Action: January 31, 2019: Awarded professional engineering contract 219-070 to HDR Engineering Inc. for an amount of $111,925 to conduct preliminary engineering and prepare Technical Memorandums for the Various Drainage Improvements project.

City Council Strategic Initiative:  [Please select from the dropdown menu below]

Sustainability

Choose an item.

Choose an item.

 

Comprehensive Plan Element (s): [Please select the Plan element(s) and Goal # from dropdown menu below]
Economic Development - Choose an item.
Environment & Resource Protection - Population Prepared for and resilient to Man-Made & Natural Disasters
Land Use - Choose an item.
Neighborhoods & Housing - Choose an item.
Parks, Public Spaces & Facilities - Choose an item.
Transportation - Choose an item.

Core Services

Not Applicable

Master Plan
: [Please select the corresponding Master Plan from the dropdown menu below (if applicable)]
Stormwater Master Plan

 

Background Information:

This request is to obtain Council approval for Authorization for Change in Service (ACIS #2) to engineering contract 219-070 with HDR for the additional design and construction phase services for four sites identified in the Stormwater Master Plan.  Phase 1 of this contract developed recommendations to correct drainage issues at seven (7) sites.  Based upon Phase 1, estimated construction costs and available funding, the following four projects will move forward

                     Bishop/Prospect Street Drainage Improvements - New storm drain improvements along Bishop and Prospect streets consisting of new pipe, curb inlets and a 4-way open inlet.

                     S. LBJ Drive at Willow Springs Bridge Repair - Repair of spalls and cracks in sections of the existing concrete box culverts.

                     Hutchinson Storm Drain Improvements (LBJ to Guadalupe) - New storm drain system including pipes and inlets on E. Hutchison Street (near Fire Station No.1) to replace a collapsed line and provide a stormwater connection to the Kissing Alley project.

                     Drainage Ditch Outfall to Cradock Storm Drain - New storm drain to connect an existing ditch to a storm drain located on Craddock Avenue.  Will improve drainage complaints in the Castle Forrest neighborhood.

 

It is anticipated the projects will be grouped into two construction packages in order to achieve economy of scale for construction.

 

The current schedule is for the designs to be completed by October and construction starting in December 2021.

 

Council Committee, Board/Commission Action:
NA
Alternatives:

NA


Recommendation: 

Staff recommends approval of ACIS #2 to add design and construction phase services to HDR Engineering, Inc. contract.