Skip to main content
File #: Res. 2024-41R    Version: 1 Name:
Type: Resolution Status: Individual Consideration
File created: 2/26/2024 In control: City Council
On agenda: 3/19/2024 Final action:
Title: Consider approval of Resolution 2024-41R, approving a contract with Chain Electric Company, through the City's interlocal agreement with the City of New Braunfels, for the provision of Indefinite Delivery Indefinite Quantity ("IDIQ") fiber optic installation, maintenance, and repair services in an estimated annual amount of $700,000.00; authorizing the City Manager, or her designee, to execute the contract on behalf of the city; and declaring an effective date.
Attachments: 1. Resolution
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

AGENDA CAPTION:

Title

Consider approval of Resolution 2024-41R, approving a contract with Chain Electric Company, through the City’s interlocal agreement with the City of New Braunfels, for the provision of Indefinite Delivery Indefinite Quantity (“IDIQ”) fiber optic installation, maintenance, and repair services in an estimated annual amount of $700,000.00; authorizing the City Manager, or her designee, to execute the contract on behalf of the city; and declaring an effective date.

Body

Meeting date:  March 19, 2024

 

Department:  Information Technology Department - Mike Sturm, Director

 

Amount & Source of Funding
Funds Required:
  $700,000 annually

Account Number:  Various, project-dependent

Funds Available:  $700,000 CIP Budgeted

Account Name:  Various, project-dependent

 

Fiscal Note:
Prior Council Action: Click or tap here to enter text.

City Council Strategic Initiative:  [Please select from the dropdown menu below]

Choose an item.

Choose an item.

Choose an item.

 

Comprehensive Plan Element (s): [Please select the Plan element(s) and Goal # from dropdown menu below]
Economic Development - Choose an item.
Environment & Resource Protection - Choose an item.
Land Use - Choose an item.
Neighborhoods & Housing - Choose an item.
Parks, Public Spaces & Facilities - Choose an item.
Transportation - Choose an item.

Core Services

Not Applicable

Master Plan
: [Please select the corresponding Master Plan from the dropdown menu below (if applicable)]
Choose an item.


Background Information:

The City of San Marcos is entering into an annual services agreement 224-162 with Chain Electric Company, located in Hattiesburg, Mississippi, for Indefinite Delivery Indefinite Quantity (IDIQ) Fiber Optic Installation, Maintenance, and Repair Services through its interlocal agreement with the City of New Braunfels. 

 

The contract allows the city to procure services for the installation of fiber optic cabling and the acquisition of necessary equipment for the installation process. The purpose of the fiber optic cabling is to expand the city's network connectivity to various city-owned facilities, including electric substations, pump and lift stations, traffic registers, communication towers, water towers, and other field assets that require high-speed connectivity. The installation of the fiber optic cabling will involve utilizing existing utility poles and underground conduits, both current and future.

 

The estimated annual contract amount is $700,000 and will automatically renew each year for a total contract term of five (5) years.  Therefore, the total estimated amount of the contract is $3,500,000.  The City retains the option to not renew, if needed.

 

The City of San Marcos is authorized to participate in interlocal agreements per Local Government Code, Section 271.  As such, the City is utilizing its cooperative purchasing agreement with City of New Braunfels to enter into this agreement with Chain Electric Company.

 

Council Committee, Board/Commission Action:
Click or tap here to enter text.

Alternatives:

Click or tap here to enter text.


Recommendation: 

Staff recommends approval of the IDIQ Fiber Optic Installation, Maintenance, and Repair Services with Chain Electric Company.