Title: Consider approval of Resolution 2023-22R, awarding a construction contract to Qro Mex Construction, Inc. for the West Purgatory Creek Wastewater Improvement project in the estimated amount of $2,381,741.00; authorizing the City Manager or her designee to execute the contract on behalf of the City; and declaring an effective date.
Attachments: 1. Resolution, 2. Location Map, 3. Eng's Bid Recomendation_Purgatory Creek, 4. Box Culvert Outfall, 5. 222-214 Bid Tabulation

GENDA CAPTION:

Title

Consider approval of Resolution 2023-22R, awarding a construction contract to Qro Mex Construction, Inc. for the West Purgatory Creek Wastewater Improvement project in the estimated amount of $2,381,741.00; authorizing the City Manager or her designee to execute the contract on behalf of the City; and declaring an effective date.

Body

Meeting date:  January 17, 2023

 

Department:   Engineering and Capital Improvements, Shaun Condor, Director (by Lynda Williams, Purchasing & Contracting Manager)

 

Amount & Source of Funding
Funds Required:
  $2,381,741.00

Account Number:  Multiple Accounts

 

Funds Available:

C546 - www - $2,097,096.98

C546 - drainage - $424,475.04

 

Account Name:  West Purgatory Creek Wastewater Improvements

 

Fiscal Note:
Prior Council Action: Resolution 2022-155R approval of design, bid and construction phase services for Bowman Consulting Group Ltd.

City Council Strategic Initiative:  [Please select from the dropdown menu below]

Sustainability

Choose an item.

Choose an item.

 

Comprehensive Plan Element (s): [Please select the Plan element(s) and Goal # from dropdown menu below]
☐ Economic Development - Choose an item.
☒ Environment & Resource Protection - Population Prepared for and resilient to Man-Made & Natural Disasters
☐ Land Use - Choose an item.
☐ Neighborhoods & Housing - Choose an item.
☐ Parks, Public Spaces & Facilities - Choose an item.
☐ Transportation - Choose an item.

☐ Core Services

☐ Not Applicable

Master Plan
: [Please select the corresponding Master Plan from the dropdown menu below (if applicable)]                     
Wastewater Master Plan

Stormwater Master Plan

Background Information:

Seven (7) bids were received on November 17, 2022, for the West Purgatory Creek WW Improvements IFB #222-214. Award is recommended to the lowest responsible bidder, Qro Mex Construction Inc., from Granite Shoals, Texas in the amount of $2,381,741.

Based on the recommendations of the COSM Wastewater Masterplan, this project proposes to replace a 12-inch wastewater line with an 18-inch line from W. San Antonio St across Purgatory Creek to Ellis Street.  This project also proposes to install a portion of an 8’x8’ box culvert outfall that will continue upstream with the Bishop & Belvin Street Improvements project.  See Location Map and Box Culvert Outfall exhibits for approximate location of both alignments. 

Construction cost for the wastewater line is $1,988,027 and $393,714 for the box culvert outfall accounting for a total of $2,381,741.  This project is scheduled to start in February 2023 and to be complete by mid-2024. 

 

Council Committee, Board/Commission Action:
N/A

Alternatives:

N/A


Recommendation: 

Staff recommends award of a construction contract to Qro Mex Construction, Inc., in the amount of $2,381,741.00.