AGENDA CAPTION:
Title
Consider approval of Resolution 2020-254R, approving the award of a contract to Electro Technical Industries, Inc for the San Marcos Electrical Utility Switchgear Building in the estimated amount of $802,300.00; authorizing the City Manager or his designee to execute the agreement on behalf of the City; and declaring an effective date.
Body
Meeting date: November 17, 2020
Department: Public Services - Tom Taggart, Director (by Lynda Williams, Purchasing Manager)
Amount & Source of Funding
Funds Required: $802,300
Account Number: C652 51538170-70200
Funds Available: $5,918,534
Account Name: Wastewater Treatment Plant Electric Backup Feed
Fiscal Note:
Prior Council Action: Approval of CIP C652 in FY18 budget cycle
City Council Strategic Initiative: [Please select from the dropdown menu below]
N/A
Choose an item.
Choose an item.
Comprehensive Plan Element (s): [Please select the Plan element(s) and Goal # from dropdown menu below]
? Economic Development - Choose an item.
? Environment & Resource Protection - Choose an item.
? Land Use - Choose an item.
? Neighborhoods & Housing - Choose an item.
? Parks, Public Spaces & Facilities - Choose an item.
? Transportation - Choose an item.
? Core Services
? Not Applicable
Master Plan: [Please select the corresponding Master Plan from the dropdown menu below (if applicable)]
Choose an item.
Background Information:
The medium voltage switchgear building is a main component for achieving project scope of increasing the electric reliability at the City's wastewater treatment plant. Once this building is in service, the City will be able to automatically transfer the plant to the backup source during outages and will gain more detailed data about the treatment plant's energy usage and power quality.
Eight (8) bids were received on October 1, 2020. The apparent low bidder failed to comply with the bidding requirements, and is therefore deemed nonresponsive making the bidder disqualifie...
Click here for full text