Title: Consider approval, by motion, of Change Order # 3 with Rocking Q Construction LLC, in the amount of $170,941.30, for the upsizing of the IH-35 bore casing from 24" to 36", replace internally restrained pipe joints with external restraints, and overlay Durango Street in connection with the Reclaimed Water Expansion Project.
Attachments: 1. CO #3 3-27-2018s, 2. Location Map Rocking Q, 3. Casing-Carrier Pipe Detail, 4. CO #3, 4-11-2018s w backup_signed.pdf
AGENDA CAPTION:
Title
Consider approval, by motion, of Change Order # 3 with Rocking Q Construction LLC, in the amount of $170,941.30, for the upsizing of the IH-35 bore casing from 24" to 36", replace internally restrained pipe joints with external restraints, and overlay Durango Street in connection with the Reclaimed Water Expansion Project.
Body
Meeting date: May 15, 2018

Department: Engineering/C.I.P.

Amount & Source of Funding
Funds Required: $170,941.30
Account Number: C258
Funds Available: $400,000
Account Name: WW Collection Improvements

Fiscal Note:
Prior Council Action: None

City Council Strategic Initiative: [Please select from the dropdown menu below]
City Facilities
Goal #5 Maintain & Improve City's Infrastructure
Choose an item.
Comprehensive Plan Element (s): [Please select the Plan element(s) and Goal # from dropdown menu below]
? Economic Development - Choose an item.
? Environment & Resource Protection - Choose an item.
? Land Use - Choose an item.
? Neighborhoods & Housing - Choose an item.
? Parks, Public Spaces & Facilities - Choose an item.
? Transportation - Choose an item.
? Not Applicable

Master Plan: [Please select the corresponding Master Plan from the dropdown menu below (if applicable)]
Choose an item.


Background Information:
Rocking Q Construction LLC is currently working on the Reclaimed Water Expansion Project and will be adding Change Order #3 to their scope of work. Change Order #3, for $170,941.30,
The change order includes the upsizing of the IH-35 bore casing from 24" to 36" and replacing internally restrained pipe joints with external restraints. When the project was initially bid, externally restrained pipe was not available. This type of pipe is preferred due to the ease in which it can be dismantled and replaced if needed for future maintenance. The upsizing of the IH-35 bore casing from 24" to 36" is required due to the size of the external joint restraints relative to the size of the carrier p...

Click here for full text